Memorandum
City of Lawrence
Public Works Department
TO: |
David L. Corliss |
FROM: |
David P. Cronin, Project Engineer |
CC: |
Charles Soules, Shoeb Uddin, Mark Thiel |
Date: |
August 25, 2009 |
RE: |
George Williams Way: 6th Street to Overland Drive – Project No. 14-CP4-407(BD) Overland Drive to North City Limits – Project No. 15-CP5-407(BD) |
Please include the following item on the City Commission consent agenda for consideration at the September 1, 2009 meeting:
Approval of Change Orders No. 7 & No. 8
-Change order 7 – Re-Stake intersection for GWW access to property on NE corner of GWW and 6th Street. |
-Change order 8 – Adding driveway onto west end of Mercato Way. Work includes temporary drainage pipe under roadway and placement of 6” aggregate 30’ wide driveway. |
All change orders are funded 100% by the benefit district; 0% by the City at large. |
Project Details: The project includes the construction of George Williams Way from 6th Street to the north city limits, including streets, sidewalks, multi-use paths, storm sewer, waterline and sanitary sewer improvements.
Project Status. The project is 95% complete and is on schedule to be completed in the allowed contract time.
Project Funding: The benefit district is paying for 100% of the cost except the city-at-large will pay $200,000. The City’s at-large share of the improvement district has not changed since the district was initially proposed in 2007.
ORIGINAL BID AMOUNT |
$2,210,153.40 |
CHANGE ORDER 1 Underdrain |
$7,500.00 |
CHANGE ORDER 2 Underdrain/Rip Rap/Filter Fabric |
$11,000.00 |
CHANGE ORDER 3 Waterline Tie in lower than Plan |
$2,180.00 |
CHANGE ORDER 4 Replace Damaged ITS conduit |
$4,725.00 |
CHANGE ORDER 5 Asphalt Adjustment |
($9126.59) |
CHANGE ORDER 6 Property Access |
$35,071.00 |
|
|
CHANGE ORDER 7 Re-stake intersection |
$880.00 |
CHANGE ORDER 8 Property Access |
$22,500.00 |
|
|
Total Amount to be approved: |
$23,380.00 |
|
|
TOTAL PROJECT COST |
$2,284,882.81 |
Action Request. Public Works staff requests approval of Change Orders No. 7 and No. 8 in the amount of $23,380.00
Respectfully Submitted,
David P. Cronin
Project Engineer