Project History.  On March 3, 2009 the City received a petition for street, water and sanitary sewer improvements for Fairfield East Addition No. 1.

The CC approved Resolution 6831 and 6832 establishing the respective benefit district.

Project DescriptionThe proposed project will include street, curb and gutter, sidewalks, water main, sanitary sewer main, and lift station/force main for the development.  The benefit district will pay 100% of the cost of the improvements.  No city funds will be used.

 

Method of Assessment

Streets, sidewalk, water main, front footage

 

       Estimated cost:

$1,666,700.00

Sanitary sewer/force main – square footage

 

       Estimated cost:

$   450,000.00

 

Project Status.  Attached is a proposed/tentative project schedule. 

 

Action Request.  Bids will be received September 1.  Staff will prepare a memo to be posted to the agenda and presented to the City Commission for Street, Sanitary Sewer, and Lift Station.  City Commission will be asked to award bids as appropriate.

 

Respectfully submitted

Charles F. Soules, P.E.

Director of Public Works

 

CFS/je

 

Attachments:  Calendar of Events/Project Schedule

                   Benefit District Map