| Barcus Bid | |||||
| Full Bid | Option 1- without Causeway | ||||
| Mobilization | $278,152.00 | $278,152.00 | |||
| Toronto Rock | $460,876.80 | ||||
| quarry | $200,353.00 | $200,353.00 | |||
| causeway | $115,140.00 | ||||
| clay liner | $15,228.89 | ||||
| truck | $79.83 | $79.83 | |||
| excavator | $135.32 | $135.32 | |||
| piling | $648,894.00 | $648,894.00 | |||
| coating | $74,271.00 | $74,271.00 | |||
| steel | $44,919.00 | $44,919.00 | |||
| kcmmb | $117,085.76 | $117,085.76 | |||
| concrete | $259,549.92 | $259,549.92 | |||
| diver mob | $1,311.71 | $1,311.71 | |||
| diver mob | $538.08 | $538.08 | |||
| all thread | $43,550.00 | $43,550.00 | |||
| walers | $38,400.00 | $38,400.00 | |||
| plates | $3,618.00 | $3,618.00 | |||
| bridge | $446,715.00 | $446,715.00 | |||
| causeway remove | $216,255.20 | ||||
| performance bond | $15,854.66 | $15,854.66 | |||
| statutory bond | $5,703.08 | $5,703.08 | |||
| ACCESS ROAD | $25,000.00 | $25,000.00 | |||
| borings | $75,000.00 | $75,000.00 | |||
| $3,086,631.25 | $2,279,130.36 | ||||