Barcus Bid
Full Bid Option 1- without Causeway
Mobilization $278,152.00 $278,152.00
Toronto Rock $460,876.80
quarry $200,353.00 $200,353.00
causeway $115,140.00
clay liner $15,228.89
truck $79.83 $79.83
excavator $135.32 $135.32
piling $648,894.00 $648,894.00
coating $74,271.00 $74,271.00
steel $44,919.00 $44,919.00
kcmmb $117,085.76 $117,085.76
concrete $259,549.92 $259,549.92
diver mob $1,311.71 $1,311.71
diver mob $538.08 $538.08
all thread $43,550.00 $43,550.00
walers $38,400.00 $38,400.00
plates $3,618.00 $3,618.00
bridge $446,715.00 $446,715.00
causeway remove $216,255.20
performance bond $15,854.66 $15,854.66
statutory bond $5,703.08 $5,703.08
ACCESS ROAD $25,000.00 $25,000.00
borings $75,000.00 $75,000.00
$3,086,631.25 $2,279,130.36