FAIRFIELD EAST ADDITION NO. 1

BENEFIT DISTRICT

PROPOSED/TENTATIVE SCHEDULE

 

July 8, 2009

Engineering drawings submitted to City

July 22, 2009

City comments received                                

July 31, 2009

Engineering drawings 2nd submittal to City       

August 7, 2009

City comments received

August 14, 2009

Final City approval of drawings

August 19, 2009

Drawings out to bid

September 1, 2009

Contractor bid deadline                                

September 1, 2009

City Commission approval of construction contract  

September 11, 2009

Construction contract executed, bond in place 

September 14, 2009

Work commences                      

January 2010

Completion