FAIRFIELD EAST ADDITION NO. 1
BENEFIT DISTRICT
PROPOSED/TENTATIVE SCHEDULE
July 8, 2009 |
Engineering drawings submitted to City |
July 22, 2009 |
City comments received |
July 31, 2009 |
Engineering drawings 2nd submittal to City |
August 7, 2009 |
City comments received |
August 14, 2009 |
Final City approval of drawings |
August 19, 2009 |
Drawings out to bid |
September 1, 2009 |
Contractor bid deadline |
September 1, 2009 |
City Commission approval of construction contract |
September 11, 2009 |
Construction contract executed, bond in place |
September 14, 2009 |
Work commences |
January 2010 |
Completion |