Memorandum
City of Lawrence
Department of Public Works
|
TO: |
David L. Corliss, City Manager |
|
FROM: |
Shoeb Uddin, City Engineer |
|
CC: |
Chuck Soules, Mark Thiel, Matt Bond, David Woosley, David Cronin, Ed McNeive, Lyle Morris, Steve Lashley |
|
DATE: |
August 05, 2009 |
|
RE: |
Set Bid Date - 2009 KLINK 23rd Street, Ousdahl Road to Barker Avenue Milling, Overlay, Permanent Marking & Geometric Improvements Public Works Project #PW0901 – City Bid #B09049 August 11, 2009 Consent Agenda Item |
Background
The “KLINK” resurfacing program of the Kansas Department of Transportation is intended to assist the local governments with the maintenance and upkeep of the City Connecting Links of the State Highway System (K-10, Hwy-59 and Hwy-40).
KDOT contributes 50% of the cost of construction and construction inspection services, up to a maximum amount of $200,000.00. The city is responsible for the remaining 50% of the cost of construction and construction inspection services. The city is also responsible for 100% of the cost of engineering design services; typically, city staff provides the engineering design services and prepares the construction plans and specification. Construction inspection is also provided by city staff.
|
- In 2006, mill and overlay of Iowa street (Irving Hill Overpass to Harvard Road) was completed as a KLINK project. (KLINK Funding received: $200,000.00) |
|
- In 2007, two sections of Iowa Street (23rd Street to Irving Hill Road overpass, Yale Road to 6th Street) received mill and overlay under the KLINK program. (KLINK Funding received: $200,000.00) |
|
- In 2008, mill and overlay of Iowa street (23rd Street to 31st Street) was also partially funded through the KLINK program. (KLINK Funding received: $200,000.00) |
Project Details / Cost
The project would consist of mill and overlay, concrete joint repair, replacement of curb inlets, curb and gutter removal and replacement etc.; project location is 23rd Street, from Ousdahl Road to Barker Avenue.
|
Estimated Total Project cost: |
$500,000.00 |
|
KLINK Funds: |
$200,000.00 |
|
City’s Share: |
$300,000.00 – Resolution 6859 authorizing GO Bonds for $225,000 and $75,000 from Street Maintenance Funds. |
Engineering Plans have been approved by KDOT and are now ready for Bid Letting. Construction will begin in mid September, 2009 with expected completion date by mid November, 2009.
Action Requested
Authorize staff to set the Bid Opening Date on August 25, 2009 for the 2009 KLINK project, 23rd Street from Ousdahl Road to Barker Avenue.
Attachment: Project Location Map