Memorandum
City of Lawrence
Public Works
|
TO:
|
David L. Corliss
|
|
FROM:
|
Mark Thiel
|
|
CC:
|
Chuck Soules, Steve Lashley, Diane Stoddard, Cynthia
Boecker, Jonathan Douglass, Tom Orzulak
|
|
Date:
|
6/30/2009
|
|
RE:
|
2009 Street
Maintenance Mid-Year Update
|
As we reach the end of June 2009
I wanted to take this opportunity to provide a mid-point update and status of
our 2009 Street Maintenance Program.
This year the City’s annual pavement maintenance
program was reviewed and approved by the City Commission on January 27, 2009
for a total contracted street maintenance program budget of $4.4 million (see 2009 budget graph). The
program included 183 lane miles of various types of maintenance projects, 40
lane miles of microsurfacing, 22 lane miles of mill and overlay, 10 miles of
curb and gutter replacement, and 121 lane miles of crack sealing (see proposed 2009
contracted street maintenance map.)
The various program projects included: Crack Sealing Program that bid
on March 3, 2009; a Curb and Gutter
Replacement Program that bid on March 24, 2009; an Overlay Program Phase 1 that
bid on April 7, 2009; the 2008 Microsurfacing Program contract was extended
with the 2009 Microsurfacing Program street locations; overlay of W. 9th
Street from Tennessee to Iowa (Sales Tax Program Rehabilitation Project) was
bid on June 2, 2009; Phase II Overlay Program
bid June 30, 2009, and upcoming
KLINK overlay of W. 23rd Street from Ousdahl Road to Barker Avenue
that will bid in July 2009. As a result of the contractor bids being below our
engineer’s estimate we have been able to perform some additional unplanned
work, i.e. Oread Inn concrete street improvements and 10th Street, Delaware
to Pennsylvania,
mill and overlay.
At present we are assessing our project budgets and original funding
level to determine additional projects that will extend our 2009 contracted
street maintenance program, gaining us additional progress. Some of the
potential areas include downtown parking lot, phase III overlay, alleys, and a
concrete street rehabilitation project.
The microsurfacing project is 65 percent complete. Our contractor will
be back in July to complete the remaining sections of pavement. This year we
extended the 2008 contract through an agreement with our contractor locking in
the 2008 bid pricing for the 2009 programmed streets. This was a cost savings
to the City of Lawrence
of $0.60 per square yard or $96,162.00. The microsurfacing maintenance project
continues to grow and gain us much needed improvements to our infrastructure at
a minimal cost compared to a full blow overlay. The cost comparison for
microsurfacing versus overlay is $3.00 versus $14.00. We are able with this
maintenance tool to effectively improve our pavement condition while at the
same time make efficient use of programmed dollars (see microsurfacing
map and photos).
The crack sealing project is 100 percent complete and included 121 lane
miles. Crack sealing remains an inexpensive but effective way to extend the
life of pavement. By sealing cracks and keeping penetrating moisture from
getting into the subgrade we can proactively minimize the potential for future
potholes and surface deterioration. Ideally we would like to program our street
sections to be cracked sealed every 3 to 5 years. This is probably the most
effective protection for our streets at a very minimal cost (see crack seal map and photo).
The concrete curb and gutter replacement project is 75 percent
complete. This remains a popular maintenance project. Often the adjacent
roadway is still in great shape and not in need of maintenance at the same time
of the curb replacement. This is also a cost effective way to perform only
required maintenance. Curbs serve as a channel to drain water from our roadways
into our storm water system. Damaged curbs often pond water thus presenting a
situation where the water will seep into the subgrade and eventually begin to
deteriorate the adjacent pavement (see curb and gutter map and
photo.)
Phase I mill and overlay is 100 percent complete. This project went very
smoothly and was completed in less than 60 days. Phase II mill and overlay bid
on June 30th and will be presented to the City Commission on July 7th
for approval to award. This is a much larger overlay project and key highlighted
areas include Naismith Drive
from 19th to 23rd, Alabama
and 21st Street
adjacent to the Lawrence
High School, bike shared
lanes on Naismith, concrete intersection approach at 23rd Street, and conversion of
traffic loop detection of video detection at the intersection of 19th
and Naismith and 23rd and Naismith. Scheduled completion of Naismith Drive will
be no later than August 14th; the remaining portion of Phase II
shall be completed no later than 75 days after the notice to proceed (see phase 1 and 2 maps and
photo.)
Construction of Timberedge
Road began in May of 2009 and was part of the 2008
street maintenance program. It was identified as a roadway section that had
completely deteriorated and was in sever need of reconstruction. Good pricing
for other 2008 maintenance projects allowed us to fund this project. As part of
this project we completely rebuilt 800 feet of Timberedge Road. This project was
completed in June and resulted in a new 10” concrete street with new curbs. (Timberedge photos attached)
The 2009 KLINK project will bid in July of 2009. It will include
milling and overlaying 23rd
Street from Ousdahl to Barker Avenue. Other key items on this
project may include the conversion of traffic loop detection to video
detection, if additional funding can be identified. There is significant cost
savings to the city by upgrading to the video detection at the time of the
overlay. This eliminates the cost of the loop detection that can be used toward
the video system. Several studies have proven that video detection has several
advantages over the loop detection. KLINK is a cost share project between the
city and KDOT.
A highlight this year to our street maintenance program is the 9th Street
overlay and traffic safety improvement project from Iowa
to Tennessee.
This project is the first street
maintenance project to include funding from the recently approved
infrastructure sales tax initiative. Work on this project includes mill and
overlay, curb replacements, and widening of the intersection of 9th
and Avalon to include a turn lane on 9th
Street. This project began June 10, the day after
Commission approval and award, and has been progressing ahead of schedule. The
first section of 9th
Street from Iowa
to Emery, which included the widening at Avalon, was completed two weeks ahead
of schedule. The contractor continues to make significant progress and is
currently working on Avalon and the section of 9th Street from Emery to Mississippi. This
project is scheduled to be completed mid August 2009. We are currently reviewing with the Traffic
Safety Committee and the Bicycle Advisory Committee the possibility of adding
bike lanes on portions of 9th
Street. The
findings of this study will be presented at a future Commission meeting. (9th street photos attached)
Public Works is currently evaluating phase II of our street rating
program (see pavement
condition rating map) which is scheduled to be completed August 2009. We
will use that data along with an evaluation of our 2009 project budget balance
to determine additional projects for this year’s maintenance program. We are
currently looking at several possible areas that will enhance our current maintenance
program. We would like to be able to perform a concrete street rehabilitation
project – possible street section would include Inverness,
Bluffs Drive, West
Hills Terrace and West Hills Drive,
and Baker Drive.
This would add an additional maintenance program to our current program
enabling us to work toward proper maintenance and repair of our existing
concrete streets before an expensive overlay or total replacement would be
needed. Next year Public Works will have completed a five year projected
maintenance plan that will greatly increase our effectiveness in programming
street sections for upcoming years maintenance. We believe our program is
working, and continued support from the City and Commission has given us the
ability to make progress. We have also developed a street maintenance pamphlet
that has been published and posted on our web site. This pamphlet details our
street maintenance program and gives the public a resource to better understand
our program. (pamphlet
attached)
In summary, we are making significant progress toward improving the
roadways in Lawrence.
The 2009 program is ahead of the 2008 program in terms of completeness through
June. We worked over the winter to move our projects up to be ready to begin
the program in early spring of 2009 which has proved to be very effective. By the end of
August 2009 we will be 90 percent complete with the 2009 Street Maintenance Program
- three months ahead of last year. In addition to the contracted street
maintenance program it is note worthy to mention that our in-house Street Division
has complemented our contracted program in many ways. They have been out ahead
of our contractors performing in-house maintenance to eliminate down time and
delays to contractors. They have played a significant role in this year’s
coordinated effort to perform street maintenance. The Street Division plays a
key role in the day to day maintenance and operation of our roadways.
Please let me know if you have
any questions.