Memorandum
City of
Public Works
TO: |
Dave
Corliss, City Manager |
FROM: |
|
CC: |
Chuck
Soules, Diane Stoddard, Matt Bond |
Date: |
June
25, 2009 |
RE: |
Bowersock Dam Proposed Rehabilitation and Repair Plan (PRRP) |
Bowersock Dam was constructed in the 1870’s. Information
about the original construction is unknown; as a result, there is an unavoidable
element of uncertainty (that may require field adjustments) in the Proposed
Rehabilitation and Repair Plan (PRRP) outlined in this memo. It is, however,
important to note that the PRRP has been developed based on the results and recommendations
of previous engineering studies, proposals, field data, and consultations and conceptual
concurrence with experienced engineers, contractors, and various state and
federal agencies with jurisdictional authority over Bowersock Dam.
City Staff, in consultation with representatives from
Bowersock Dam, Hamm Construction and United Construction (United is the
contractor for the KTA bridge over the
1.
Build a Rock Work Platform (Rock Cofferdam / Causeway)
upstream of the dam, face up stream side, with clay. Pump out water between the work platform
and the dam which will enable closer and thorough examination of the extent
of leaks and damage on the upstream face of the dam. |
2.
There is a lot of concrete debris and riprap from the
old highway bridges. Some of this
material will need to be removed in order to drive the sheet piling. |
3.
Backfill the area between the sheet piles and dam and
place a concrete cap. |
4.
Repair cracks, holes, erosions, and gaps in the existing
dam to protect the timber structure.
These repairs were previously recommended and received concurrence
from city staff, Bowersock Mill and various state and federal agencies. |
5.
This
work will provide
a long term solution for the north half of the dam. |
6.
The south half of the dam is a masonry structure that
appears to be stable (not leaking through the structure); however, there is a
scoured area on the downstream side.
Repair of this area is not included in this project scope. |
The PRRP has to be carried out during low flow season
in the river; low flow period in the river typically ranges from August through
February. In order to ensure completion of this project before February of
2010, it is important that this project proceeds as quickly as possible with a start
date preferably in August 2009. Maintaining low outflow from the upstream dams
(Perry, Tuttle Creek and
Project Cost /Funding
Estimate cost for the work outlined is approximately
$2-2.5 million. Staff is currently
exploring the potential for funding from various other state and federal
sources. Additional stakeholders may
include Bowersock Mill, KDOT, Westar, and KU.
There have been significant discussions with Hamm
Construction and United Construction about this project. This estimate is staff’s best effort at this
time without being able to physically examine the site. It needs to be realized that costs may
increase/decrease based upon what the condition of the face of the dam actually
is, and/or the depth of rock will affect pile driving efforts.
Hamm Construction has been involved with this project
for several months. They have
considerable knowledge about the challenges and opportunities associated with
this project.
With the KTA river crossing, we also have an
opportunity to work with a large contractor, United Construction, who are very
experienced working in this environment.
United Construction has significant equipment, material, and personnel resources
in
Permitting Requirements
Permits from state and federal agencies will have to
be obtained prior to beginning work on the dam. Staff has been in contact with
all agencies (Federal Regulatory Commission, Corps of Engineers, Kansas
Division of Water Resources, Kansas Wildlife and Parks) and has obtained
commitment for an expedited permitting process. Typically, some of these
agencies take up to 6 months to review Permit application. It is anticipated
that all necessary permits will be in place by August 15, 2009.
In order to proceed further the City needs to confirm
the scope of the project. This will
allow staff to formally submit applications and request funding.
|
|
|
|
|
|
|
|
|