2009 Revenue Bond Project Descriptions
- Waterline
Rehabilitation and Replacement Program – Staff continuously evaluates the condition of the water
distribution system based on mainbreaks, pipe material and age, capacity
and fire protection needs. Based on these criteria, along with the
criticality of the watermain within the system and the number of services
affected, watermains are targeted for replacement. This project will
design and construct the watermains chosen for replacement.
- Ground Storage Tanks
Rehabilitation: Oread & Clinton WTP – The two existing Oread water storage tanks and pump station were
constructed in the 1930’s and 1950’s and have reached the end of their
useful lives. This project will study the replacement of the two tanks
with a single tank and begin design of the study recommended improvements.
The study will investigate the feasibility of the water system to function
temporarily without the two tanks or the interim measures that would be
needed to operate the system while the new tank is constructed.
The
repainting of the Clinton ground storage tanks would target specific areas
where the coating is failing. These repairs will maintain the integrity of the
coating and the tanks.
- Wastewater Pump Station
Improvements – The project
includes improvements to the prioritized list of vacuum prime pump
stations throughout the City including Pump Station 27. These pump
stations are in need of replacement for capacity and mechanical
reliability issues. The pump stations would be replaced with submersible
stations that meet current department design standards for operations and
safety.
Pump
Station 28 is in need of replacement due to limit capacity and incidents of
backups. This pump station can be eliminated and the flows redirected to Pump
Station 35. Pump Station 35 would then be reconstructed with this project to
serve as a regional pump station.
- Anaerobic Digester
Improvements at the Lawrence Wastewater Treatment Plant – The project involves the design of a thermal
dyer dewatering process and odor control, associated modifications to the
existing biosolids dewatering building to accommodate the dryer
installation, modifications to existing piping and valves in the solids
and gas control buildings, installation of insulation on the concrete roof
of Digester 1, modifications to the gas control building/equipment to
allow processing of additional digester gas and an evaluation of energy
recovery from the digester gas system. This project is required to
increase the capacity of the wastewater plant’s solids processing stream
to match the plant’s liquid processing capacity and provide treatment for
a community of 100,000 persons.