Memorandum
City of Lawrence
Public Works Department
TO: |
David L. Corliss |
FROM: |
David P. Cronin, Project Engineer |
CC: |
Charles Soules, Shoeb Uddin, Mark Thiel |
Date: |
April 29, 2009 |
RE: |
George Williams Way: 6th St. to Overland Dr. – Proj. No. 14-CP4-407(BD) Overland Dr. to North City Limits – Proj. No. 15-CP5-407(BD) |
Please include the following item on the City Commission consent agenda for consideration at the May 5, 2009 meeting:
Approval of Change Orders No. 1 & 2 Change order 1 is for an underdrain system adjacent to edge of roadway to facilitate subsurface drainage. Change order 2 includes work to aid slope stability and drainage through a large roadside cut section.
Total change order amount is $18,500.00. All change orders are funded 100% by the benefit district; 0% by the City at large.
Project Details: The project includes the construction of George Williams Way from 6th Street to the north city limits, including streets, sidewalks, multi-use paths, storm sewer, waterline and sanitary sewer improvements.
Project Status. The project is 35% complete and is on schedule to be completed in the allowed contract time.
Project Funding: The benefit district is paying for 100% of the cost except the city-at-large will pay $200,000. The City’s at-large share of the improvement district has not changed since the district was initially proposed in 2007.
ORIGINAL BID AMOUNT $2,210,153.40 |
CHANGE ORDER 1 Underdrain $7,500.00 |
CHANGE ORDER 2 Underdrain/Rip Rap/Filter Fabric $11,000.00 |
|
Total Amount to be approved: $18,500.00 |
|
TOTAL PROJECT COST $2,228,653.40 |
Action Request. Public Works staff requests approval of Change Orders No. 1 & 2 in the amount of $18,500.00
Respectfully Submitted,
David P. Cronin
Project Engineer