The following work has been completed or is currently in progress.

 

 

 

Areas of concern to be addressed within the next few weeks include replacing all other deteriorated structural members which may include floor joists, sub floors and wall studs.  Focus will then shift to the porch reconstruction.

 

Pictures are attached which identify the work completed.

 

 

 

 

 

 

 

 

 

 

 

 

 

 

       

 

   SE corner – complete foundation reconstruction and new sill plate for exterior wall

 

 

 

 

    

 

East wall – complete foundation reconstruction and new sill plate for exterior wall.

 

 

 

 

 

 

 

 

 

 

The south foundation wall repair of the west addition.  The corner still

needs to have stone laid and then tuck pointed.

 

    Roof repair in progress on west

                                                                                               addition

The north elevation (street view).  This roof repair

 is completed. 

 

 

 

 

 

 

Area where large hole existed prior to repair.

 

 

Interior view of roof repair in the NE 2nd floor bedroom.

 

 

Interior view of the roof repair in the NW 2nd floor bedroom that had experienced

significant damage.