Memorandum
City of Lawrence
Planning & Development Services
TO: |
David L. Corliss, City Manager
|
FROM: |
Brian Jimenez, Code Enforcement Manager
|
CC: |
Scott McCullough, Director Planning and Development Services
|
Date: |
April 3, 2009
|
RE: |
617 W 4th St; Update on progress of rehabilitation
|
The following work has been completed or is currently in progress.
Areas of concern to be addressed within the next few weeks include replacing all other deteriorated structural members which may include floor joists, sub floors and wall studs. Focus will then shift to the porch reconstruction.
Pictures are attached which identify the work completed.
SE corner – complete foundation reconstruction and new sill plate for exterior wall
East wall – complete foundation reconstruction and new sill plate for exterior wall.
The south foundation wall repair of the west addition. The corner still
needs to have stone laid and then tuck pointed.
Roof
repair in progress on west
addition
The north elevation (street view). This roof repair
is completed.
Area where large hole existed prior to repair.
Interior view of roof repair in the NE 2nd floor bedroom.
Interior view of the roof repair in the NW 2nd floor bedroom that had experienced
significant damage.