Memorandum
City of Lawrence
Utilities Department
TO: |
David L. Corliss – City Manager Cynthia Boecker - Assistant City Manager Diane Stoddard - Assistant City Manager |
FROM: |
Philip Ciesielski – Asst. Director of Utilities |
CC: |
Dave Wagner – Director of Utilities Mike Lawless – Asst. Director of Utilities Beth Frailey Krishtalka – Management Analyst Dave King – Utility Maintenance Manager |
Date: |
March 4, 2009 |
RE: |
March 10, 2009 Agenda Item – Advertise RFP for Design and Construction Phase Engineering Services for Option 4 the replacement of the Waste Water Plant Administrative Building Heating, Ventilation and Air Conditioning (HVAC) system. |
Please include the following item on the City Commission Agenda for consideration at the March 10, 2009 meeting:
Authorize Staff to advertise a Request for Proposals for Design and Construction Phase Engineering Services for Option 4 the replacement of the Waste Water Plant Administrative Building Heating, Ventilation and Air Conditioning (HVAC) system.
Project Description
Over the last year, and through the Department’s reorganization, the Administrative Building at the Waste Water Treatment Plant has become the main Administrative Office building for Department of Utilities. This building now houses the Director of Utilities, Assistant Director, Management Analyst, Utilities Programs Manager and Administrative Assistant staff in addition to the previously assigned operations and lab staff. The building is staffed 24 hours a day with operators. In addition as the location of the Director of Utilities’ office the building hosts numerous staff, project and other Departmental meetings and is designated as the Department’s first option as an Emergency Command Center should the need arise. The building also houses sensitive computer, server, process control and laboratory equipment.
The existing HVAC system in this building consists of several standalone systems dating from 1976 and 2000. Each of these systems; the multi-zone control, chiller and heating, while examples of the available technology at the time of installation, are independent and do not communicate with each other. The age of the existing system components has resulted in current maintenance and component replacement needs in order for the existing system to meet the heating and cooling needs of the building. These immediate needs include the air handling unit and a compressor on the chiller unit.
Project Status/Details
Based on the current maintenance needs, operational limitations of the existing systems and the energy efficiency of the existing systems, Staff engaged Hoss & Brown Engineers for a survey, evaluation and subsequent recommendation for repairs, rehabilitation, or replacement of the existing HVAC system. As a follow-up to the recommendations and capital costs provided in the initial report, Staff requested an additional analysis of the energy costs for each proposed option. This information was used in recommending Option 4 the replacement of the existing systems.
Hoss & Brown’s survey and evaluation of the existing systems resulted in three proposed options to address the repair and operational requirements of the existing systems. These included varying degrees of replacement of the chiller, repairs to the existing air handling unit and modifications to the duct work, to the replacement of the HVAC system and duct work and the establishment of control zones throughout the building.
Based on the evaluation of each option’s capital costs, additional maintenance and parts costs on partial replacement options, and resulting 20 year electric and natural gas costs, Option 4 the replacement of the HVAC system is the recommended alternative. See the table below for a summary of the cost comparison.
|
Total Project Cost = Capital + 20 yrs Energy |
|||
Energy Inflation Factor |
|
2.50% |
5% |
10% |
Total Project Cost = Capital + 20 yrs Energy |
Capital Cost |
Total Project |
Total Project |
Total Project |
Option 1 - immediate repairs - future maint/replacement costs not included |
$15,000.00 |
$458,736.25 |
$589,388.69 |
$1,009,924.02 |
Option 2 - partial replacement - future maint/replacement costs not included |
$157,256.00 |
$533,528.81 |
$644,317.50 |
$1,000,916.74 |
Option 3 - partial replacement - future maint/replacement costs not included |
$215,937.00 |
$475,572.90 |
$552,019.36 |
$798,080.09 |
Option 4 - complete replacement |
$363,011.00 |
$602,032.36 |
$672,409.13 |
$898,933.17 |
Option 4** - est. reduce energy by 15% with zones |
$363,011.00 |
$566,179.16 |
$625,999.41 |
$818,544.84 |
The estimated capital and energy costs are reflected in the above table. Additional factors considered in the evaluation not fully quantified in the table above include; the costs associated with the ongoing maintenance and ultimate replacement of aging system components left after Options 1, 2 or 3 which consist of partial repair or system replacement at this time; the additional energy savings resulting from complete system replacement (Option 4**); and the ability to discretely partition the building spaces and only condition those spaces occupied at different times of the workday and week; i.e. conference rooms and office spaces in the evening and weekends. As shown in the table the cost advantage obtained with the complete replacement is magnified as the cost of energy rises.
Project Funding:
The recommended replacement has been included in the Department of Utilities proposed Capital Improvement Projects and Rate Plans. These projects will be funded from the 2008 Utility Department Capital General Wastewater Treatment Plant Improvements Fund.
Action Request: Authorize Staff to advertise a Request for Proposals for Design and Construction Phase Engineering Services for Option 4 replacement of the Waste Water Plant Administrative Building Heating, Ventilation and Air Conditioning (HVAC) system.
Thank you for your assistance. Please advise if you have any questions.