COMPREHENSIVE HOUSING REHABILITATION SCOPE OF WORK:
2703 Bonanza St. – Trim overhanging tree. Install new shingles, gutter, downspouts and in-ground drain system. Replace damaged siding, window trim and paint exterior. Replace handrail. Install new countertop and sink in bathroom. Replace floor coverings in bath, kitchen and entry areas. Replace kitchen faucet and install crown molding. Provide GFCI protection in kitchen and bath. Window repairs in kitchen, bedroom and basement. Install new lighting fixture for stairs and repair basement lighting and outlets in basement. Install new water heater.
B09011 |
Bid |
Comet Corp. |
$14,875.00 |
T&J Holdings |
$17,130.00 |
Penny Const. Inc. |
$23,126.00 |
Staff Estimate |
$14,158.70 |
936 Pennsylvania St – Trim overhanging tree branches and point foundation cracks. Repair roof decking, replace flat and sloped roofing, tuck point chimney and install new gutters and downspouts. Repair siding shingles, soffit, fascia trim, corner trim and paint exterior wood on house and garage. Replace sidewalk and steps. Install jamb liners, sill covers and make repairs to windows. Install new hot water heating system complete. Install new water heater.
B09012 |
Base Bid |
Alternate 1 |
T & J Holdings, Inc. |
No bid |
No bid |
Comet Corp. |
$37,355.00 |
$1,500.00 |
Penny Construction |
$39,226.00 |
$1,000.00 |
Staff Estimate |
$28,066.80 |
$200.00 |
829 Ohio St – Prep and paint exterior of house and shed. Replace furnace and install duct work to serve upstairs bedrooms. Replace water heater and install sump pit and pump. Modify closet and paint bedroom. Refinish door, complete trim in bathroom, install footed tub faucet, shower and shower curtain. Repair several windows, laminate plaster ceiling, modify base cabinet rough in for dish washer and install new countertop with sink. Rebuild roof framing on shed and install shingle roof.
B09013 |
Base Bid |
Alternate 1 |
T & J Holdings, Inc. |
No bid |
No bid |
Comet Corp. |
$21,060.00 |
$1,080.00 |
Penny Construction |
$23,887.00 |
$1,000.00 |
Staff Estimate |
$20,147.15 |
$1,250.00 |
Recommendation Action:
2703 Bonanza St.: Award bid, to Comet Corp. for $14,875.00.
936 Pennsylvania St: Reject all bids. Exceeds program cost limits.
829 Ohio St: Award bid, to Comet Corp. for $22,140.00.