Memorandum

City of Lawrence

Public Works Department

 

TO:

David L. Corliss

FROM:

David P. Cronin, Project Engineer

CC:

Charles Soules, Mark Thiel

Date:

February 4, 2009

RE:

25th Terrace, O’Connell Road to Franklin Road

Project No. 12-CP2-407(BD)

 

Please include the following item on the City Commission consent agenda for consideration at the February 10, 2009 meeting:

Approval of Change Orders No. 4 (additional) thru 10 for 25th Terrace, O’Connell Road to Franklin Rd.   Change orders 1 thru 4 were approved on May 13, 2008.   Change orders 4 (additional) through 10 cover all outstanding items. Total change order amount is $117,631.05.  All change orders are funded 100% by the benefit district; 0% by the City at large.

 

Project Status.  The project is 100% complete and was completed within the contract allowable time.

 

Project Funding. The total project cost is funded 100% from the benefit district; 0% by the City at large.  The estimated construction costs for the benefit district was $2,590,000.00.

 

ORIGINAL BID AMOUNT 

$1,457,591.30

 

 

CHANGE ORDER 1

Sanitary Sewer (Reimbursed by the County)

$27,643.00

CHANGE ORDER 2

Deletion of Side Roads        

-$21,541.82

CHANGE ORDER 3

Additional Grading and Erosion Control 

$37,862.00

CHANGE ORDER 4

Edge Drain    

  $6,765.00

  Amount approved by CC on May 13, 2008

$50,728.18

 

 

 

CHANGE ORDER 4

(additional) Edge Drain

$3,433.75

CHANGE ORDER 5

Steel Plates as required by Southern Star

$4,200.00

CHANGE ORDER 6

Asphalt oil fuel adjustment

$71,946.15

CHANGE ORDER 7

Electric Meter for Lights

$575.00

CHANGE ORDER 8

Additional site work

$2,660.00

CHANGE ORDER 9

Final Field Measurements   

-$30,912.03

CHANGE ORDER 10

Queen Pond Dam Restoration (paid to Mr. Queen)

$15,000.00

Total Amount to be approved:       

$66,902.87

 

 

TOTAL PROJECT COST

 

$1,575,222.35

 

Action Request.  Public Works staff requests approval of Change Orders No. 4 (additional) thru 10 in the amount of $66,902.87

 

Respectfully Submitted,

David P. Cronin

Project Engineer