Memorandum
City of Lawrence
Department of Public Works
TO: |
David L. Corliss, City Manager |
FROM: |
Walter Ward, City Surveyor |
CC: |
Chuck Soules, Shoeb Uddin, Lyle Morris, Mark Thiel |
Date: |
January 21, 2009 |
RE: |
Project No. PW 0816 – City Bid No. B09006 Set Bid Date for 2008 Sidewalk Gap Program |
Please include the referenced item on the City Commission agenda for consideration at the January 27, 2009 meeting:
Project Details: A sidewalk gap and rehabilitation program in the low and moderate income areas of the City was recommended by the Community Development Advisory Committee (CDAC) and approved by the City Commission.
Plans and specifications for this project have been completed by City engineering staff and the project is ready for bid letting. All construction work will be within existing city right of way; there will be no cost for property acquisition. All adjacent property owners have been notified about the project.
Project History:
December 1, 2007 |
Submitted the application for Community Development Block Grant (CDBG) funds to the Community Development Division for inclusion in 2008 program year proposals. |
January-April, 2008 |
Community Development Advisory Committee (CDAC) review proposals and complete recommendation regarding CDBG funding. |
May 6, 2008 |
City Commission reviews CDAC recommendations and approves funding for sidewalk gap program and sidewalk rehabilitation in the low and moderate income areas (see attached map). |
Summer-Fall, 2008 |
Sidewalk plans developed by City staff. |
Project Schedule:
February 17, 2009 |
Bid Opening |
April, 2009 – October, 2009 |
Construct project |
Project Funding: 100% of the construction cost of this project will be paid by the Community Development Block Grant (CDBG).
Action Request: Set Bid Date of February 17, 2009 for City Bid No. B09006, Project No. PW 0816, 2008 Sidewalk Gap Program.
Attachment: Map