Memorandum
City of Lawrence
Department of Public Works
TO: |
David L. Corliss |
FROM: |
Steven Lashley |
CC: |
Charles Soules |
Date: |
September 4, 2008 |
RE: |
2008 Overlay Program, Phase 1- Change Order No.1 and Final |
Please include the referenced item on the City Commission consent agenda for consideration at the September 16, 2008 meeting:
Project Description. The 2008 Overlay Program Phase 1 (PW0808) project is part of the annually contracted pavement maintenance program. The work included milling and overlaying of streets in and near the downtown Lawrence area which included Massachusetts from 6th to North Park, 7th from Vermont to New Jersey, New Jersey from 7th to 8th, and Kentucky from 6th to 12th.
Project Details. The original contract bid price amounted to $491,995.60. Due to significant increases in asphalt oil prices, this project saw an overall increase in the asphalt cost of $48,731.00. Other quantities in the project were reduced by approximately $11,298.60 leaving a net increase to the original contract of $37,432.40.
Project Funding. The overrun will be paid from the 2008 contracted street maintenance funds, account #001-3000-570.45-08.
Action Request. Approve Change Order No. 1 to LRM Industries Inc. in the amount of $37,432.40.
Respectfully submitted,
Steven M. Lashley, P.E.
Project Engineer – Infrastructure Management