CITY
OF LAWRENCE |
|
|
|
|
|
|
|
|
|
City Bid No. 08066 |
|
|
|
Project No. PW0820 - 2008
Overlay Program, Phase 3 |
|
|
Bid Date: July 29, 2008 |
|
|
|
Engineer's Estimate: |
|
|
|
Base Bid Grand Total:
$843,715.00 |
|
|
|
|
|
Kansas Heavy
Construction |
R. D. Johnson |
LRM Industries |
ITEM |
DESCRIPTION |
UNITS |
QUANTITY |
UNIT PRICE |
AMOUNT |
UNIT PRICE |
AMOUNT |
UNIT PRICE |
AMOUNT |
Base Bid Section - 2008
Overlay Program, Phase 3 |
|
|
|
|
|
|
1 |
Milling
(2") |
SY |
42,231 |
$ 1.40 |
$ 59,123.40 |
$
1.30 |
$ 54,900.30 |
$
1.45 |
$ 61,234.95 |
2 |
Asphaltic
Concrete Overlay Surface Course (2") |
TONS |
5,041 |
$
62.00 |
$ 312,542.00 |
$
62.00 |
$ 312,542.00 |
$
61.00 |
$ 307,501.00 |
3 |
Asphaltic
Concrete Overlay Leveling Course* |
TONS |
581 |
$
64.00 |
$ 37,184.00 |
$
64.00 |
$ 37,184.00 |
$
69.00 |
$ 40,089.00 |
4 |
Asphalt
Pavement Patch * |
TONS |
274 |
$
100.00 |
$ 27,400.00 |
$
100.00 |
$ 27,400.00 |
$
115.00 |
$ 31,510.00 |
5 |
Concrete
Pavement Patch * |
SY |
780 |
$
56.20 |
$ 43,836.00 |
$
75.00 |
$ 58,500.00 |
$
61.00 |
$ 47,580.00 |
6 |
6"
Concrete Pavement (Reinforced) |
SY |
475 |
$
51.00 |
$ 24,225.00 |
$
65.00 |
$ 30,875.00 |
$
49.50 |
$ 23,512.50 |
7 |
8"
Concrete Pavement (Reinforced) |
SY |
255 |
$
63.40 |
$ 16,167.00 |
$
70.00 |
$ 17,850.00 |
$
61.00 |
$ 15,555.00 |
8 |
24"
Concrete Curb and Gutter |
LF |
8,775 |
$
19.60 |
$ 171,990.00 |
$
20.00 |
$ 175,500.00 |
$
21.30 |
$ 186,907.50 |
9 |
Install
6" Underdrain Line |
LF |
535 |
$
17.00 |
$ 9,095.00 |
$
8.00 |
$ 4,280.00 |
$
13.75 |
$ 7,356.25 |
10 |
Driveway
Wedges* |
SY |
630 |
$
11.00 |
$ 6,930.00 |
$
11.00 |
$ 6,930.00 |
$
9.50 |
$ 5,985.00 |
11 |
Crackfilling
up to 1" width* |
LF |
12,290 |
$
0.55 |
$ 6,759.50 |
$
0.55 |
$ 6,759.50 |
$
0.48 |
$ 5,899.20 |
12 |
Manhole
Adjustment |
EACH |
6 |
$
470.00 |
$ 2,820.00 |
$
500.00 |
$ 3,000.00 |
$
525.00 |
$ 3,150.00 |
13 |
Valve
Adjustment |
EACH |
5 |
$
150.00 |
$ 750.00 |
$
130.00 |
$ 650.00 |
$
155.00 |
$ 775.00 |
14 |
Cold
Plastic Reflectorized Pavement Marking |
|
|
|
$ - |
|
$ - |
|
$ - |
|
a) 6" Solid White Edge Line |
LF |
260 |
$
7.35 |
$ 1,911.00 |
$
7.35 |
$ 1,911.00 |
$
7.25 |
$ 1,885.00 |
|
b) 6" Solid Yellow Edge Line |
LF |
240 |
$
7.35 |
$ 1,764.00 |
$
7.35 |
$ 1,764.00 |
$
7.25 |
$ 1,740.00 |
|
c) 4" Solid Double Yellow Lane Line ** |
LF |
50 |
$
10.50 |
$ 525.00 |
$
10.50 |
$ 525.00 |
$
10.45 |
$ 522.50 |
|
d) 24" Solid White Stop Line |
LF |
20 |
$
23.35 |
$ 467.00 |
$
23.25 |
$ 465.00 |
$
23.00 |
$ 460.00 |
15 |
Asphalt Test Core* |
EACH |
10 |
$
70.00 |
$ 700.00 |
$
70.00 |
$ 700.00 |
$
55.00 |
$ 550.00 |
16 |
Temporary Surfacing* |
TONS |
200 |
$
23.00 |
$ 4,600.00 |
$
20.00 |
$ 4,000.00 |
$
20.00 |
$ 4,000.00 |
17 |
Seeding, Fertilizing, and Mulching |
LS |
1 |
$ 3,250.00 |
$ 3,250.00 |
$
1,500.00 |
$ 1,500.00 |
$
10,000.00 |
$ 10,000.00 |
18 |
Traffic Control |
N/A |
1 |
Force Account |
$ 30,000.00 |
Force Account |
$ 30,000.00 |
Force Account |
$ 30,000.00 |
Total Base Bid Section |
$
762,038.90 |
$
777,235.80 |
$
786,212.90 |
|
ITEM |
DESCRIPTION |
UNITS |
QUANTITY |
UNIT PRICE |
AMOUNT |
UNIT PRICE |
AMOUNT |
UNIT PRICE |
AMOUNT |
Alternate Bid Section A |
|
|
|
|
|
|
1 |
Milling
(2") |
SY |
10,217 |
$ 1.60 |
$ 16,347.20 |
$
1.60 |
$ 16,347.20 |
$
1.75 |
$ 17,879.75 |
2 |
Asphaltic
Concrete Overlay Surface Course (2") |
TONS |
1,220 |
$ 65.00 |
$ 79,300.00 |
$
65.00 |
$ 79,300.00 |
$
61.80 |
$ 75,396.00 |
3 |
Asphaltic
Concrete Overlay Leveling Course* |
TONS |
141 |
$ 66.00 |
$ 9,306.00 |
$
66.00 |
$ 9,306.00 |
$
76.75 |
$ 10,821.75 |
4 |
Asphalt
Pavement Patch * |
TONS |
30 |
$ 100.00 |
$ 3,000.00 |
$
100.00 |
$ 3,000.00 |
$
115.00 |
$ 3,450.00 |
5 |
Concrete
Pavement Patch * |
SY |
310 |
$ 78.00 |
$ 24,180.00 |
$
75.00 |
$ 23,250.00 |
$
61.15 |
$ 18,956.50 |
6 |
6"
Concrete Pavement (Reinforced) |
SY |
170 |
$ 60.00 |
$ 10,200.00 |
$
62.00 |
$ 10,540.00 |
$
50.00 |
$ 8,500.00 |
7 |
8"
Concrete Pavement (Reinforced) |
SY |
55 |
$ 75.00 |
$ 4,125.00 |
$
70.00 |
$ 3,850.00 |
$
61.45 |
$ 3,379.75 |
8 |
24"
Concrete Curb and Gutter |
LF |
2,500 |
$
19.60 |
$ 49,000.00 |
$
20.00 |
$ 50,000.00 |
$
21.40 |
$ 53,500.00 |
9 |
Concrete
Sidewalk (4") |
SY |
20 |
$
40.00 |
$ 800.00 |
$
40.00 |
$ 800.00 |
$
44.60 |
$ 892.00 |
10 |
Concrete
Access Ramp |
EACH |
2 |
$
1,260.00 |
$ 2,520.00 |
$
1,350.00 |
$ 2,700.00 |
$
1,415.00 |
$ 2,830.00 |
11 |
Driveway
Wedges* |
SY |
180 |
$
11.00 |
$ 1,980.00 |
$
11.00 |
$ 1,980.00 |
$
11.50 |
$ 2,070.00 |
12 |
Crackfilling
up to 1" width* |
LF |
3,750 |
$
0.55 |
$ 2,062.50 |
$
0.55 |
$ 2,062.50 |
$
0.50 |
$ 1,875.00 |
13 |
Asphalt Test Core* |
EACH |
3 |
$
70.00 |
$ 210.00 |
$
70.00 |
$ 210.00 |
$
55.00 |
$ 165.00 |
14 |
Temporary Surfacing* |
TONS |
50 |
$
23.00 |
$ 1,150.00 |
$
20.00 |
$ 1,000.00 |
$
20.00 |
$ 1,000.00 |
15 |
Seeding, Fertilizing, and Mulching |
LS |
1 |
$ 1,000.00 |
$ 1,000.00 |
$
3,000.00 |
$ 3,000.00 |
$
10,000.00 |
$ 10,000.00 |
16 |
Traffic Control |
N/A |
1 |
Force Account |
$ 5,000.00 |
Force Account |
$ 5,000.00 |
Force Account |
$ 5,000.00 |
Total Alternate Bid Section A |
$
210,180.70 |
$
212,345.70 |
$
215,715.75 |
|
ITEM |
DESCRIPTION |
UNITS |
QUANTITY |
UNIT PRICE |
AMOUNT |
UNIT PRICE |
AMOUNT |
UNIT PRICE |
AMOUNT |
Alternate Bid Section B |
|
|
|
|
|
|
1 |
Milling
(2") |
SY |
7,373 |
$ 1.95 |
$ 14,377.35 |
$
1.60 |
$ 11,796.80 |
$
1.45 |
$ 10,690.85 |
2 |
Asphaltic
Concrete Overlay Surface Course (2") |
TONS |
880 |
$ 65.00 |
$ 57,200.00 |
$
65.00 |
$ 57,200.00 |
$
63.60 |
$ 55,968.00 |
3 |
Asphaltic
Concrete Overlay Leveling Course* |
TONS |
102 |
$ 66.00 |
$ 6,732.00 |
$
66.00 |
$ 6,732.00 |
$
78.60 |
$ 8,017.20 |
4 |
Asphalt
Pavement Patch * |
TONS |
304 |
$ 100.00 |
$ 30,400.00 |
$
100.00 |
$ 30,400.00 |
$
115.00 |
$ 34,960.00 |
5 |
6"
Concrete Pavement (Reinforced) |
SY |
135 |
$ 60.00 |
$ 8,100.00 |
$
62.00 |
$ 8,370.00 |
$
50.00 |
$ 6,750.00 |
6 |
8"
Concrete Pavement (Reinforced) |
SY |
45 |
$ 75.00 |
$ 3,375.00 |
$
70.00 |
$ 3,150.00 |
$
54.00 |
$ 2,430.00 |
7 |
24"
Concrete Curb and Gutter |
LF |
5,535 |
$ 21.50 |
$ 119,002.50 |
$
20.00 |
$ 110,700.00 |
$
21.40 |
$ 118,449.00 |
8 |
Crackfilling
up to 1" width* |
LF |
1,700 |
$ 0.55 |
$ 935.00 |
$
0.55 |
$ 935.00 |
$
0.53 |
$ 901.00 |
9 |
Valve
Adjustment |
EACH |
3 |
$ 175.00 |
$ 525.00 |
$
130.00 |
$ 390.00 |
$
155.00 |
$ 465.00 |
10 |
Asphalt Test Core* |
EACH |
2 |
$
70.00 |
$ 140.00 |
$
70.00 |
$ 140.00 |
$
55.00 |
$ 110.00 |
11 |
Temporary Surfacing* |
TONS |
150 |
$
23.00 |
$ 3,450.00 |
$
20.00 |
$ 3,000.00 |
$
20.00 |
$ 3,000.00 |
12 |
Seeding, Fertilizing, and Mulching |
LS |
1 |
$ 3,200.00 |
$ 3,200.00 |
$
3,000.00 |
$ 3,000.00 |
$
8,000.00 |
$ 8,000.00 |
13 |
Traffic Control |
N/A |
1 |
Force Account |
$ 5,000.00 |
Force Account |
$ 5,000.00 |
Force Account |
$ 5,000.00 |
Total Alternate Bid Section B |
$
252,436.85 |
$
240,813.80 |
$
254,741.05 |
|
ITEM |
DESCRIPTION |
UNITS |
QUANTITY |
UNIT PRICE |
AMOUNT |
UNIT PRICE |
AMOUNT |
UNIT PRICE |
AMOUNT |
Alternate Bid Section C - Municipal Airport
Taxiway Apron (Area A) |
|
|
|
|
|
|
1 |
Common
Excavation (4" Pavement/Subgrade Removal) |
CY |
218 |
$ 42.00 |
$ 9,156.00 |
$
17.20 |
$ 3,749.60 |
$
38.50 |
$ 8,393.00 |
2 |
Asphaltic
Concrete Overlay Surface Course (4") |
TONS |
470 |
$
66.00 |
$ 31,020.00 |
$
66.00 |
$ 31,020.00 |
$
64.10 |
$ 30,127.00 |
3 |
Asphalt Test Core* |
EACH |
1 |
$
70.00 |
$ 70.00 |
$
70.00 |
$ 70.00 |
$
55.00 |
$ 55.00 |
Alternate Bid Section C - Municipal Airport Taxiway Apron (Area
B) |
|
|
|
|
|
|
1 |
Common
Excavation (4" Pavement/Subgrade Removal) |
CY |
59 |
$ 42.00 |
$ 2,478.00 |
$
20.00 |
$ 1,180.00 |
$
38.50 |
$ 2,271.50 |
2 |
Asphaltic
Concrete Overlay Surface Course (4") |
TONS |
127 |
$
66.00 |
$ 8,382.00 |
$
66.00 |
$ 8,382.00 |
$
65.50 |
$ 8,318.50 |
3 |
Asphalt Test Core* |
EACH |
1 |
$
70.00 |
$ 70.00 |
$
70.00 |
$ 70.00 |
$
55.00 |
$ 55.00 |
Total Alternate Bid Section C |
$
51,176.00 |
$
44,471.60 |
$
49,220.00 |
|
ITEM |
DESCRIPTION |
UNITS |
QUANTITY |
UNIT PRICE |
AMOUNT |
UNIT PRICE |
AMOUNT |
UNIT PRICE |
AMOUNT |
Alternate Bid Section D - Lawrence Memorial Park Cemetery |
|
|
|
|
|
|
1 |
Asphaltic
Concrete Overlay Surface Course (2") |
TONS |
1,000 |
$ 70.00 |
$ 70,000.00 |
$
65.80 |
$ 65,800.00 |
$
63.65 |
$ 63,650.00 |
2 |
Asphalt
Pavement Patch* |
TONS |
100 |
$
100.00 |
$ 10,000.00 |
$
100.00 |
$ 10,000.00 |
$
115.00 |
$ 11,500.00 |
3 |
Asphalt Test Core* |
EACH |
2 |
$
70.00 |
$ 140.00 |
$
70.00 |
$ 140.00 |
$
55.00 |
$ 110.00 |
Total Alternate Bid Section D |
$
80,140.00 |
$
75,940.00 |
$
75,260.00 |
|
ITEM |
DESCRIPTION |
UNITS |
QUANTITY |
UNIT PRICE |
AMOUNT |
UNIT PRICE |
AMOUNT |
UNIT PRICE |
AMOUNT |
Alternate Bid Section E - 8th-9th St Speed Cushions |
|
|
|
|
|
|
1 |
Earthwork |
LS |
1 |
$ 2,250.00 |
$ 2,250.00 |
$
850.00 |
$ 850.00 |
$
250.00 |
$ 250.00 |
2 |
Removal
of Existing Pavement |
LS |
1 |
$
4,500.00 |
$ 4,500.00 |
$
2,350.00 |
$ 2,350.00 |
$
1,700.00 |
$ 1,700.00 |
3 |
Aggregate
Base (6") (AB-3) |
SY |
108 |
$
16.00 |
$ 1,728.00 |
$
9.00 |
$ 972.00 |
$
11.80 |
$ 1,274.40 |
4 |
Speed
Cushion |
EACH |
3 |
$
7,850.00 |
$ 23,550.00 |
$
5,078.00 |
$ 15,234.00 |
$
5,600.00 |
$ 16,800.00 |
Total Alternate Bid Section E |
$
32,028.00 |
$
19,406.00 |
$
20,024.40 |
|
|
TOTAL BASE BID SECTION |
|
$
762,038.90 |
|
$
777,235.80 |
|
$
786,212.90 |
|
|
TOTAL
ALTERNATE BIDS |
|
$
625,961.55 |
|
$
592,977.10 |
|
$
614,961.20 |
|
|
|
|
|
|
|
|
|
TOTAL BASE
BID + ALTERNATE BIDS |
|
$
1,388,000.45 |
|
$
1,370,212.90 |
|
$
1,401,174.10 |
|
|
|
|
|
|
|
|
|
|