| CITY OF LAWRENCE | |||||||||
| City Bid No. 08066 | |||||||||
| Project No. PW0820 - 2008 Overlay Program, Phase 3 | |||||||||
| Bid Date: July 29, 2008 | |||||||||
| Engineer's Estimate: | |||||||||
| Base Bid Grand Total: $843,715.00 | |||||||||
| Kansas Heavy Construction | R. D. Johnson | LRM Industries | |||||||
| ITEM | DESCRIPTION | UNITS | QUANTITY | UNIT PRICE | AMOUNT | UNIT PRICE | AMOUNT | UNIT PRICE | AMOUNT |
| Base Bid Section - 2008 Overlay Program, Phase 3 | |||||||||
| 1 | Milling (2") | SY | 42,231 | $ 1.40 | $ 59,123.40 | $ 1.30 | $ 54,900.30 | $ 1.45 | $ 61,234.95 |
| 2 | Asphaltic Concrete Overlay Surface Course (2") | TONS | 5,041 | $ 62.00 | $ 312,542.00 | $ 62.00 | $ 312,542.00 | $ 61.00 | $ 307,501.00 |
| 3 | Asphaltic Concrete Overlay Leveling Course* | TONS | 581 | $ 64.00 | $ 37,184.00 | $ 64.00 | $ 37,184.00 | $ 69.00 | $ 40,089.00 |
| 4 | Asphalt Pavement Patch * | TONS | 274 | $ 100.00 | $ 27,400.00 | $ 100.00 | $ 27,400.00 | $ 115.00 | $ 31,510.00 |
| 5 | Concrete Pavement Patch * | SY | 780 | $ 56.20 | $ 43,836.00 | $ 75.00 | $ 58,500.00 | $ 61.00 | $ 47,580.00 |
| 6 | 6" Concrete Pavement (Reinforced) | SY | 475 | $ 51.00 | $ 24,225.00 | $ 65.00 | $ 30,875.00 | $ 49.50 | $ 23,512.50 |
| 7 | 8" Concrete Pavement (Reinforced) | SY | 255 | $ 63.40 | $ 16,167.00 | $ 70.00 | $ 17,850.00 | $ 61.00 | $ 15,555.00 |
| 8 | 24" Concrete Curb and Gutter | LF | 8,775 | $ 19.60 | $ 171,990.00 | $ 20.00 | $ 175,500.00 | $ 21.30 | $ 186,907.50 |
| 9 | Install 6" Underdrain Line | LF | 535 | $ 17.00 | $ 9,095.00 | $ 8.00 | $ 4,280.00 | $ 13.75 | $ 7,356.25 |
| 10 | Driveway Wedges* | SY | 630 | $ 11.00 | $ 6,930.00 | $ 11.00 | $ 6,930.00 | $ 9.50 | $ 5,985.00 |
| 11 | Crackfilling up to 1" width* | LF | 12,290 | $ 0.55 | $ 6,759.50 | $ 0.55 | $ 6,759.50 | $ 0.48 | $ 5,899.20 |
| 12 | Manhole Adjustment | EACH | 6 | $ 470.00 | $ 2,820.00 | $ 500.00 | $ 3,000.00 | $ 525.00 | $ 3,150.00 |
| 13 | Valve Adjustment | EACH | 5 | $ 150.00 | $ 750.00 | $ 130.00 | $ 650.00 | $ 155.00 | $ 775.00 |
| 14 | Cold Plastic Reflectorized Pavement Marking | $ - | $ - | $ - | |||||
| a) 6" Solid White Edge Line | LF | 260 | $ 7.35 | $ 1,911.00 | $ 7.35 | $ 1,911.00 | $ 7.25 | $ 1,885.00 | |
| b) 6" Solid Yellow Edge Line | LF | 240 | $ 7.35 | $ 1,764.00 | $ 7.35 | $ 1,764.00 | $ 7.25 | $ 1,740.00 | |
| c) 4" Solid Double Yellow Lane Line ** | LF | 50 | $ 10.50 | $ 525.00 | $ 10.50 | $ 525.00 | $ 10.45 | $ 522.50 | |
| d) 24" Solid White Stop Line | LF | 20 | $ 23.35 | $ 467.00 | $ 23.25 | $ 465.00 | $ 23.00 | $ 460.00 | |
| 15 | Asphalt Test Core* | EACH | 10 | $ 70.00 | $ 700.00 | $ 70.00 | $ 700.00 | $ 55.00 | $ 550.00 |
| 16 | Temporary Surfacing* | TONS | 200 | $ 23.00 | $ 4,600.00 | $ 20.00 | $ 4,000.00 | $ 20.00 | $ 4,000.00 |
| 17 | Seeding, Fertilizing, and Mulching | LS | 1 | $ 3,250.00 | $ 3,250.00 | $ 1,500.00 | $ 1,500.00 | $ 10,000.00 | $ 10,000.00 |
| 18 | Traffic Control | N/A | 1 | Force Account | $ 30,000.00 | Force Account | $ 30,000.00 | Force Account | $ 30,000.00 |
| Total Base Bid Section | $ 762,038.90 | $ 777,235.80 | $ 786,212.90 | ||||||
| ITEM | DESCRIPTION | UNITS | QUANTITY | UNIT PRICE | AMOUNT | UNIT PRICE | AMOUNT | UNIT PRICE | AMOUNT |
| Alternate Bid Section A | |||||||||
| 1 | Milling (2") | SY | 10,217 | $ 1.60 | $ 16,347.20 | $ 1.60 | $ 16,347.20 | $ 1.75 | $ 17,879.75 |
| 2 | Asphaltic Concrete Overlay Surface Course (2") | TONS | 1,220 | $ 65.00 | $ 79,300.00 | $ 65.00 | $ 79,300.00 | $ 61.80 | $ 75,396.00 |
| 3 | Asphaltic Concrete Overlay Leveling Course* | TONS | 141 | $ 66.00 | $ 9,306.00 | $ 66.00 | $ 9,306.00 | $ 76.75 | $ 10,821.75 |
| 4 | Asphalt Pavement Patch * | TONS | 30 | $ 100.00 | $ 3,000.00 | $ 100.00 | $ 3,000.00 | $ 115.00 | $ 3,450.00 |
| 5 | Concrete Pavement Patch * | SY | 310 | $ 78.00 | $ 24,180.00 | $ 75.00 | $ 23,250.00 | $ 61.15 | $ 18,956.50 |
| 6 | 6" Concrete Pavement (Reinforced) | SY | 170 | $ 60.00 | $ 10,200.00 | $ 62.00 | $ 10,540.00 | $ 50.00 | $ 8,500.00 |
| 7 | 8" Concrete Pavement (Reinforced) | SY | 55 | $ 75.00 | $ 4,125.00 | $ 70.00 | $ 3,850.00 | $ 61.45 | $ 3,379.75 |
| 8 | 24" Concrete Curb and Gutter | LF | 2,500 | $ 19.60 | $ 49,000.00 | $ 20.00 | $ 50,000.00 | $ 21.40 | $ 53,500.00 |
| 9 | Concrete Sidewalk (4") | SY | 20 | $ 40.00 | $ 800.00 | $ 40.00 | $ 800.00 | $ 44.60 | $ 892.00 |
| 10 | Concrete Access Ramp | EACH | 2 | $ 1,260.00 | $ 2,520.00 | $ 1,350.00 | $ 2,700.00 | $ 1,415.00 | $ 2,830.00 |
| 11 | Driveway Wedges* | SY | 180 | $ 11.00 | $ 1,980.00 | $ 11.00 | $ 1,980.00 | $ 11.50 | $ 2,070.00 |
| 12 | Crackfilling up to 1" width* | LF | 3,750 | $ 0.55 | $ 2,062.50 | $ 0.55 | $ 2,062.50 | $ 0.50 | $ 1,875.00 |
| 13 | Asphalt Test Core* | EACH | 3 | $ 70.00 | $ 210.00 | $ 70.00 | $ 210.00 | $ 55.00 | $ 165.00 |
| 14 | Temporary Surfacing* | TONS | 50 | $ 23.00 | $ 1,150.00 | $ 20.00 | $ 1,000.00 | $ 20.00 | $ 1,000.00 |
| 15 | Seeding, Fertilizing, and Mulching | LS | 1 | $ 1,000.00 | $ 1,000.00 | $ 3,000.00 | $ 3,000.00 | $ 10,000.00 | $ 10,000.00 |
| 16 | Traffic Control | N/A | 1 | Force Account | $ 5,000.00 | Force Account | $ 5,000.00 | Force Account | $ 5,000.00 |
| Total Alternate Bid Section A | $ 210,180.70 | $ 212,345.70 | $ 215,715.75 | ||||||
| ITEM | DESCRIPTION | UNITS | QUANTITY | UNIT PRICE | AMOUNT | UNIT PRICE | AMOUNT | UNIT PRICE | AMOUNT |
| Alternate Bid Section B | |||||||||
| 1 | Milling (2") | SY | 7,373 | $ 1.95 | $ 14,377.35 | $ 1.60 | $ 11,796.80 | $ 1.45 | $ 10,690.85 |
| 2 | Asphaltic Concrete Overlay Surface Course (2") | TONS | 880 | $ 65.00 | $ 57,200.00 | $ 65.00 | $ 57,200.00 | $ 63.60 | $ 55,968.00 |
| 3 | Asphaltic Concrete Overlay Leveling Course* | TONS | 102 | $ 66.00 | $ 6,732.00 | $ 66.00 | $ 6,732.00 | $ 78.60 | $ 8,017.20 |
| 4 | Asphalt Pavement Patch * | TONS | 304 | $ 100.00 | $ 30,400.00 | $ 100.00 | $ 30,400.00 | $ 115.00 | $ 34,960.00 |
| 5 | 6" Concrete Pavement (Reinforced) | SY | 135 | $ 60.00 | $ 8,100.00 | $ 62.00 | $ 8,370.00 | $ 50.00 | $ 6,750.00 |
| 6 | 8" Concrete Pavement (Reinforced) | SY | 45 | $ 75.00 | $ 3,375.00 | $ 70.00 | $ 3,150.00 | $ 54.00 | $ 2,430.00 |
| 7 | 24" Concrete Curb and Gutter | LF | 5,535 | $ 21.50 | $ 119,002.50 | $ 20.00 | $ 110,700.00 | $ 21.40 | $ 118,449.00 |
| 8 | Crackfilling up to 1" width* | LF | 1,700 | $ 0.55 | $ 935.00 | $ 0.55 | $ 935.00 | $ 0.53 | $ 901.00 |
| 9 | Valve Adjustment | EACH | 3 | $ 175.00 | $ 525.00 | $ 130.00 | $ 390.00 | $ 155.00 | $ 465.00 |
| 10 | Asphalt Test Core* | EACH | 2 | $ 70.00 | $ 140.00 | $ 70.00 | $ 140.00 | $ 55.00 | $ 110.00 |
| 11 | Temporary Surfacing* | TONS | 150 | $ 23.00 | $ 3,450.00 | $ 20.00 | $ 3,000.00 | $ 20.00 | $ 3,000.00 |
| 12 | Seeding, Fertilizing, and Mulching | LS | 1 | $ 3,200.00 | $ 3,200.00 | $ 3,000.00 | $ 3,000.00 | $ 8,000.00 | $ 8,000.00 |
| 13 | Traffic Control | N/A | 1 | Force Account | $ 5,000.00 | Force Account | $ 5,000.00 | Force Account | $ 5,000.00 |
| Total Alternate Bid Section B | $ 252,436.85 | $ 240,813.80 | $ 254,741.05 | ||||||
| ITEM | DESCRIPTION | UNITS | QUANTITY | UNIT PRICE | AMOUNT | UNIT PRICE | AMOUNT | UNIT PRICE | AMOUNT |
| Alternate Bid Section C - Municipal Airport Taxiway Apron (Area A) | |||||||||
| 1 | Common Excavation (4" Pavement/Subgrade Removal) | CY | 218 | $ 42.00 | $ 9,156.00 | $ 17.20 | $ 3,749.60 | $ 38.50 | $ 8,393.00 |
| 2 | Asphaltic Concrete Overlay Surface Course (4") | TONS | 470 | $ 66.00 | $ 31,020.00 | $ 66.00 | $ 31,020.00 | $ 64.10 | $ 30,127.00 |
| 3 | Asphalt Test Core* | EACH | 1 | $ 70.00 | $ 70.00 | $ 70.00 | $ 70.00 | $ 55.00 | $ 55.00 |
| Alternate Bid Section C - Municipal Airport Taxiway Apron (Area B) | |||||||||
| 1 | Common Excavation (4" Pavement/Subgrade Removal) | CY | 59 | $ 42.00 | $ 2,478.00 | $ 20.00 | $ 1,180.00 | $ 38.50 | $ 2,271.50 |
| 2 | Asphaltic Concrete Overlay Surface Course (4") | TONS | 127 | $ 66.00 | $ 8,382.00 | $ 66.00 | $ 8,382.00 | $ 65.50 | $ 8,318.50 |
| 3 | Asphalt Test Core* | EACH | 1 | $ 70.00 | $ 70.00 | $ 70.00 | $ 70.00 | $ 55.00 | $ 55.00 |
| Total Alternate Bid Section C | $ 51,176.00 | $ 44,471.60 | $ 49,220.00 | ||||||
| ITEM | DESCRIPTION | UNITS | QUANTITY | UNIT PRICE | AMOUNT | UNIT PRICE | AMOUNT | UNIT PRICE | AMOUNT |
| Alternate Bid Section D - Lawrence Memorial Park Cemetery | |||||||||
| 1 | Asphaltic Concrete Overlay Surface Course (2") | TONS | 1,000 | $ 70.00 | $ 70,000.00 | $ 65.80 | $ 65,800.00 | $ 63.65 | $ 63,650.00 |
| 2 | Asphalt Pavement Patch* | TONS | 100 | $ 100.00 | $ 10,000.00 | $ 100.00 | $ 10,000.00 | $ 115.00 | $ 11,500.00 |
| 3 | Asphalt Test Core* | EACH | 2 | $ 70.00 | $ 140.00 | $ 70.00 | $ 140.00 | $ 55.00 | $ 110.00 |
| Total Alternate Bid Section D | $ 80,140.00 | $ 75,940.00 | $ 75,260.00 | ||||||
| ITEM | DESCRIPTION | UNITS | QUANTITY | UNIT PRICE | AMOUNT | UNIT PRICE | AMOUNT | UNIT PRICE | AMOUNT |
| Alternate Bid Section E - 8th-9th St Speed Cushions | |||||||||
| 1 | Earthwork | LS | 1 | $ 2,250.00 | $ 2,250.00 | $ 850.00 | $ 850.00 | $ 250.00 | $ 250.00 |
| 2 | Removal of Existing Pavement | LS | 1 | $ 4,500.00 | $ 4,500.00 | $ 2,350.00 | $ 2,350.00 | $ 1,700.00 | $ 1,700.00 |
| 3 | Aggregate Base (6") (AB-3) | SY | 108 | $ 16.00 | $ 1,728.00 | $ 9.00 | $ 972.00 | $ 11.80 | $ 1,274.40 |
| 4 | Speed Cushion | EACH | 3 | $ 7,850.00 | $ 23,550.00 | $ 5,078.00 | $ 15,234.00 | $ 5,600.00 | $ 16,800.00 |
| Total Alternate Bid Section E | $ 32,028.00 | $ 19,406.00 | $ 20,024.40 | ||||||
| TOTAL BASE BID SECTION | $ 762,038.90 | $ 777,235.80 | $ 786,212.90 | ||||||
| TOTAL ALTERNATE BIDS | $ 625,961.55 | $ 592,977.10 | $ 614,961.20 | ||||||
| TOTAL BASE BID + ALTERNATE BIDS | $ 1,388,000.45 | $ 1,370,212.90 | $ 1,401,174.10 | ||||||