Memorandum

City of Lawrence

Department of Public Works

 

TO:

David L. Corliss, City Manager

FROM:

Steven Lashley, Project Engineer

CC:

Charles Soules, Director of Public Works

Date:

July 23, 2008

RE:

KLINK- Change Order No.1 and Final

 

Please include the referenced item on the City Commission consent agenda for consideration at the August 5, 2008 meeting:

 

Project DescriptionState highways that enter the City limits are referred to as “Connecting Links”.  The State offers funding assistance up to a maximum of $200,000.   Funding is obtained through application.  The City applies annually.

 

Project Details.  The KLINK (Kansas Connecting Link) Program project for 2008 included Iowa Street from 23rd Street to North of 31st Street.  The original contract bid price amounted to $422,854.45.  Due to significant increases in asphalt oil prices, this project saw an overall increase in the asphalt cost of $54,932.25.  Other quantities in the project were reduced by approximately $35,036.58 leaving a net increase to the original contract of $19,895.67.

 

Project Funding.  KDOT participates in funding up to a maximum of $200,000 through the KLINK Program for major maintenance projects on state highways.  On April 15, 2008, Resolution No. 6763 authorized General Obligation Bonds in the amount of $450,000.  The City’s share will total $242,750.12.

 

Action Request.  Approve Change Order No. 1 to Asphalt Improvement Co. in the amount of $19,895.67. 

 

Respectfully submitted,

 

Steven M. Lashley, P.E.

Project Engineer – Infrastructure Management