Memorandum
City of Lawrence
Public Works
TO: |
Chuck Soules, Public Works Director |
FROM: |
Shoeb Uddin, City Engineer |
CC: |
Dave Corliss, Cynthia Boecker, Diane Stoddard, Sheila Stogsdill, David Woosley, Scott McCullough, Jonathan Douglass , John Miller |
Date: |
July 16, 2008 |
RE: |
Resolution 6778 Ordering the Improvement and Authorizing the Issuance of General Obligation Bonds for 6th Street ITS Project City Project No. PW0823 July 22, 2008 Consent Agenda Item |
City-State Agreement for this project is currently under review at the legal departments of KDOT and the city. Once the review process is complete, this agreement will be placed on the City Commission agenda for approval.
The total estimated cost for this project is $500,000.00 and will be financed through a 50/50 contribution by KDOT and the city. Therefore, city’s matching share for this project is $250,000.00.
Engineering Design and construction plans will be completed this fall with construction to begin in the spring of 2009.
If appropriate, approve Resolution 6778 ordering the improvements for 6th Street ITS Project and authorizing the issuance of general obligation bonds for the maximum principal amount of $250,000.00