KLINK RESURFACING OF STATE HIGHWAY

FISCAL YEAR - 2011

Preliminary Project Cost Estimate

23rd Street (K-10) From Haskell Avenue To East City Limit

July 01, 2008

 

 

No.

Description

Unit

Quantity

Unit Price

Extension

1.

Milling (2”)

SY

27,000

$         1.50

$  40,500.00

2.

Asphalt Overlay (2”)

Ton

3,000

70.00

210,000.00

3.

Concrete Pavement Patching

SY

512

110.00

56,320.00

4.

Pavement Marking

LF

25,000

3.00

75,000.00

5.

Stormwater Inlets

EA

4

5,000.00

20,000.00

6.

Curb and Gutter

LF

500

25.00

12,500.00

7.

Water Pollution Control

LS

n/a

5,000.00

$5,000.00

8.

Traffic Control

LS

n/a

40,000.00

40,000.00

9.

Mobilization

LS

n/a

15,000.00

15,000.00

 

 

 

 

 

 

Total:

 

 

 

 

$474,320.00

 

 

 

 

 

 

Contingency (10%)

 

 

 

47,432.00

 

 

 

 

 

Total Construction Cost:

 

 

 

$521,752.00