KLINK RESURFACING OF STATE HIGHWAY
FISCAL YEAR - 2011
Preliminary Project Cost Estimate
23rd Street (K-10) From Haskell Avenue To East City Limit
July 01, 2008
No. |
Description |
Unit |
Quantity |
Unit Price |
Extension |
1. |
Milling (2”) |
SY |
27,000 |
$ 1.50 |
$ 40,500.00 |
2. |
Asphalt Overlay (2”) |
Ton |
3,000 |
70.00 |
210,000.00 |
3. |
Concrete Pavement Patching |
SY |
512 |
110.00 |
56,320.00 |
4. |
Pavement Marking |
LF |
25,000 |
3.00 |
75,000.00 |
5. |
Stormwater Inlets |
EA |
4 |
5,000.00 |
20,000.00 |
6. |
Curb and Gutter |
LF |
500 |
25.00 |
12,500.00 |
7. |
Water Pollution Control |
LS |
n/a |
5,000.00 |
$5,000.00 |
8. |
Traffic Control |
LS |
n/a |
40,000.00 |
40,000.00 |
9. |
Mobilization |
LS |
n/a |
15,000.00 |
15,000.00 |
|
|
|
|
|
|
Total: |
|
|
|
|
$474,320.00 |
|
|
|
|
|
|
Contingency (10%) |
|
|
|
47,432.00 |
|
|
|
|
|
|
|
Total Construction Cost: |
|
|
|
$521,752.00 |