CITY OF
LAWRENCE |
|
|
|
|
|
|
|
|
|
City Bid No. 08044 |
|
|
|
Project No. 03-TC1-108(C) -Lawrence
Avenue, Harvard Road to 9th Street |
|
|
Traffic Calming Improvements |
|
|
|
Bid Date: June 24, 2008 |
|
|
|
Engineer's Estimate: $15,920.00 |
|
|
|
|
|
LRM
Industries, Inc. |
Kansas Heavy Const. |
Comet Corporation |
ITEM |
DESCRIPTION |
UNITS |
QUANTITY |
UNIT PRICE |
AMOUNT |
UNIT PRICE |
AMOUNT |
UNIT PRICE |
AMOUNT |
1 |
Mobilization |
L.S. |
1 |
$
1,200.00 |
$ 1,200.00 |
$
1,500.00 |
$ 1,500.00 |
$
296.00 |
$ 296.00 |
2 |
Earthwork |
L.S. |
1 |
$
1,100.00 |
$ 1,100.00 |
$ 550.00 |
$ 550.00 |
$
1,110.00 |
$ 1,110.00 |
3 |
Removal of Existing
Pavement |
L.S. |
1 |
$
2,200.00 |
$ 2,200.00 |
$
1,750.00 |
$ 1,750.00 |
$
3,330.00 |
$ 3,330.00 |
4 |
Curb and Gutter, Type
CG-1 |
L.F. |
56 |
$ 20.00 |
$ 1,120.00 |
$ 34.50 |
$ 1,932.00 |
$ 25.00 |
$ 1,400.00 |
5 |
Aggregate Base
(6") (AB-3) |
S.Y. |
88 |
$ 18.00 |
$ 1,584.00 |
$ 10.00 |
$ 880.00 |
$ 29.95 |
$ 2,635.60 |
6 |
Speed Cushion |
EACH |
2 |
$
3,300.00 |
$ 6,600.00 |
$
4,150.00 |
$ 8,300.00 |
$
4,075.00 |
$ 8,150.00 |
7 |
Seeding, Mulching and
Fertilizing |
L.S. |
1 |
$ 600.00 |
$ 600.00 |
$ 400.00 |
$ 400.00 |
$
250.00 |
$ 250.00 |
8 |
Traffic Control |
L.S. |
1 |
$
1,300.00 |
$ 1,300.00 |
$
1,400.00 |
$ 1,400.00 |
$
1,550.00 |
$ 1,550.00 |
|
GRAND TOTAL |
|
|
|
$ 15,704.00 |
|
$ 16,712.00 |
|
$ 18,721.60 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|