Department
of Utilities
Memorandum
TO:
|
David Corliss – City Manager |
FROM: |
|
CC: |
|
Date: |
June 11, 2008 |
RE: |
June 17, 2008 Agenda Item – West Baldwin Creek
Interceptor Sewer Utilities
Department Project #CS0704 Award Bid |
Please include the following item on the City Commission
agenda for consideration at the June 17, 2008 meeting:
Award the bid for
Project CS0704 West
The
project began with a preliminary design-build agreement for engineering design
to be completed to a level that would allow development of a guaranteed maximum
price (GMP) for the construction of the project. A GMP was developed and a contract
prepared. Staff did not recommend
proceeding with the GMP contract and instead recommended completing the project
as a design-bid-build project to ensure a fair market value for the
construction contract.
The
project will construct approximately 15,000 feet of gravity sewers ranging in
size from 10” to 30” that were identified in the 2003 Wastewater Master Plan as
E-BC-1-02, E-BC-2-01 and E-BC-2-02. The
project will connect to and extend the gravity sewers constructed with the Pump
Station 48 project. The general area involving the project is shown on
the attached map.
Project Timeline:
July 2007:
City entered into a preliminary design-build contract with CAS
Construction/Professional Engineering Consultants (PEC) for the preliminary
design and development a GMP for the project.
November 2007:
Staff recommended not proceeding with a GMP contract for the construction of
the project.
January 2008:
City entered into a contract with PEC for completion of the design and
construction services for the project.
March 2008:
City authorized condemnation for the properties remaining to be acquired.
April 2008:
PEC finalized the bidding documents and the City Commission adopted Resolution
#6766 authorizing that bonds be issued to construct the project.
May 2008:
During the May 6, 2008 City Commission meeting a bid date of June 3, 2008 was
set for the project. The appraisal report for the remaining property to be
acquired was filed on May 29 and payment was made to the Court on June 9.
Project Status: The bid opening is complete. The
following bids were received from eleven (11) contractors;
McAninch Corporation $2,104,550.80
McCorkendale Construction $2,168,350.00
King’s Construction $2,207,728.95
Emcon Construction $2,237,000.00
Meadows Construction $2,368,710.00
Rodriguez Mechanical $2,498,085.50
Rose-Lan Contractors $2,567,397.94
Beemer Construction Co. $2,662,762.25
R.D. Johnson Excavating $3,199,999.00
Nowak Construction Co. $3,387,576.15
Engineer’s Estimate $3,967,387.00
Attached to this memo is a recommendation
from Professional Engineering Consultants to award the project to the low
bidder McAninch Corporation. As indicated in PEC’s recommendation, many
factors may have contributed to the number of bids received as well as the
pricing contained within them. Although McAninch has not worked for the City of
The
table below is included to provide a comparison of the design-build and
design-bid-build total project costs at the time of award.
|
Design-Build |
Design-Bid-Build |
GMP Development & Design Completion and Construction Services |
$
549,283.00 |
$
584,127.00 |
Construction Cost |
$3,616,000.00 |
$
2,104,550.80 |
Easements & Property Acquisition |
$
308,515.00 |
$
308,515.00 |
Permits & Misc. Costs |
$
9,000.00 |
$
9,000.00 |
Total |
$4,482,798.00 |
$
3,006,192.80 |
It
should be noted that the design-build construction cost includes $580,000.00 in
allowance costs that were to be used only if the specific scope of work was
encountered. Any allowances that were unused would not be paid as part of the
GMP contract. In the design-bid-build project, there are no allowance items.
The contractors bidding on the project must account for these items in their
bid.
We
anticipate the following schedule for the remainder of the project:
June 2008: Award construction contract.
April 2009: Final construction completion.
This
schedule is contingent upon the contract execution and weather conditions during
the construction period.
Project Funding
Funding
for the project will come from the Utilities Department Capital Improvement
Project bonded construction fund.
Action Request
Award the bid for Project CS0704
West