Memorandum
City of Lawrence
Department of Public Works
TO:
|
David L. Corliss
|
FROM:
|
Steven Lashley
|
CC:
|
Chuck Soules
|
Date:
|
June 11, 2008
|
RE:
|
Kentucky,
6th to 12th block closures - 2008 Overlay Program,
Phase 1
|
Please include this update on the City Manager’s Report for
the June 17, 2008 City Commission meeting.
Project Description/Status. The 2008 Overlay Program Phase 1
project is part of the city’s annual pavement maintenance program and was
awarded to LRM Industries, Inc. on May 20th, 2008. This contract
includes milling and overlaying streets in the downtown area including Massachusetts from 6th to North Park, 7th Street
from Vermont to New York,
and Kentucky
from 6th to 12th. The alternate bid item for the addition
of Kentucky
from 12th to 19th was deleted by addendum due to
potential conflict with proposed future waterline rehabilitation work in the
vicinity. Milling of Massachusetts began on June 4, 2008 and
currently LRM is working on Massachusetts
St between 6th and North Park St performing patching,
asphalt overlay, striping, and manhole/valve adjustments.
Project History. The city’s annual pavement maintenance
program was reviewed and approved by City Commission on March 11, 2008.
On April 9, city staff members met with Downtown Lawrence, Inc (DLI)
members to discuss issues and options associated with paving in the downtown
area. The attached outline and map were provided to those attending as part of
the presentation. The consensus of those present was that closing two to three
block sections of Massachusetts
for several days each was acceptable in order to expedite completion of the
project. It was agreed that the work on Mass must be done before the annual
sidewalk sale on July 17. (No work in the downtown area will be allowed on July
17 to accommodate the sidewalk sale.) The other primary concern was that no
work on either 7th or Kentucky that
would close lanes or impede traffic be initiated until after work on Mass. is complete. City staff has also considered events
scheduled for June 13 and 14 at 8th and New
Hampshire, and for June 19-23 at South Park
in the project planning.
Project Details. The
project includes milling existing pavement, patching deteriorated areas,
placing a 2-inch overlay pavement, installing concrete around valves and
manholes in the pavement, and pavement marking. Contract provisions include allowing closures of two to three blocks at
a time on Mass. for no more than 5 days each for paving; keeping 9th
Street open across Mass. throughout the project; maintaining at least one lane
of traffic on Kentucky at all times; and
maintaining local access to businesses on 7th St. Impacts of the work
include restrictions on on-street parking along Kentucky for a few days during the paving
work and possible detouring of some traffic. The contractor will also be
allowed to divert truck traffic using Connecticut
onto either 9th or 11th to reach New Hampshire while work is underway on 7th St.
The original traffic plan for Kentucky
was to always have one lane open to traffic during milling and paving
operations. At the pre construction meeting with the contractor we discussed
the ability for the LRM to use 2 pavers in tandem. This would improve the
paving operation, be more consistent, not have a cold joint in the pavement,
and complete the paving quicker. In order to achieve this 3 block sections of Kentucky would be closed
for 1 day each to complete the paving.
Note that other contract
provisions for maintaining at least one lane of traffic on Kentucky will still apply outside of the
days that the overlay is performed. The
three-block closures will provide LRM with the ability to perform a side by
side paving operation and enhance the potential for a more uniform pavement.
Primary work efforts will be focused on the completion of Massachusetts no later
than Friday, July 11, 2008 and will include incremental two to three block
street closures. Furthermore, no work on
any portion of the project will be allowed specifically on Thursday, July 17,
2008, during the sidewalk sale. Other
event dates have also been noted in project documents.
Project Funding. The pavement maintenance program is funded
from several sources including the general fund, gas tax funds, sales tax
reserve and capital improvement reserve accounts.