MEMORANDUM
TO: David Corliss, City Manager
FROM: Philip E. Ciesielski, P.E., Assistant Director
of Utilities
CC:
Beth Frailey Krishtalka,
Management Analyst
DATE: May 21, 2008
RE: Phase II Clinton Water Treatment
Plant Expansion 2CP205 – Approval of Change Order No. 4
Please include the following item on
the City Commission Agenda for consideration at the
May 27, 2008 meeting:
Approval of Change Order No. 4 to
the construction contract with CAS Construction LLC for the Phase II Clinton Water
Treatment Plant Expansion increasing the contract amount by $48,529.62 and
adjusting the completion dates by an additional 44 days.
Project History:
Phase I of the Clinton Water Treatment Plant (WTP)
expansion was completed in 2002 through a modified design build approach.
Phase I of the expansion improved the raw water pumping, filtering capacity,
transfer pumping and various electrical/mechanical systems. The phased
implementation of the Clinton WTP expansion provided the flexibility to the City
of
The 2003 Master Plan provided a schedule of work for completing Phase II of the expansion. The project will increase capacity to meet projected customer demands, improve reliability of the water treatment facility, and provide for future treatment processes if needed for upcoming regulations. The improvements will complete the expansion of the water treatment plant to a firm capacity of 25 million gallons per day (mgd) and hydraulic capacity to 30 mgd. This will include new basins, high service pumping, electrical improvements and miscellaneous building/chemical feed improvements.
On March 27, 2006 the following 3 base bids were received:
CAS
Construction, LLC $13,929,000.00
BRB Construction $14,351,000.00
Foley Construction $15,486,300.00
The project was awarded to CAS Construction, LLC by the
City Commission during their April 17, 2007 meeting.
Details:
Previously three (3) Change
Orders have been submitted by CAS Construction, LLC and approved by
the City. These change orders were a combination of increases and deductions
and resulted in a net increase to the contract of $26,782.05 and no change in
the contract times.
Change Order No. 4, attached,
requests a net increase to the contract of $48,529.62 for additional work and
materials, and an increase in the contract time by 44 days to account for additional
work and delays due to adverse weather conditions.
Project Schedule:
Original Contract Substantial Completion July 8, 2008
Final Completion October 16, 2008
Change Order No. 4 Substantial
Completion August 21, 2008
Final
Completion November 29,
2008
Construction
Contract Costs:
Original Contract $13,929,000.00
Change Order No.1 $11,435.09
Change Order No.2 $3,108.80
Change Order No.3 $12,238.16
Change Order No.4 $48,529.62
Current Contract Total $14,054,311.67
To date Change Order adjustments are 0.54% of the original contract amount.
Project Funding:
Funding for
the construction of the Phase II expansion, and the associate construction
phase engineering services, is come from the bonded construction fund for
2005/2007.
Action Requests: Utilities staff requests approval of Change Order No. 4 to the
construction contract with CAS Construction LLC for the Phase II Clinton Water
Treatment Plant Expansion increasing the contract amount by $48,529.62 and
adjusting the completion dates by an additional 44 days.
Thank you for your assistance. Please advise if you have any questions.