Memorandum
City of
Department of Public Works
TO: |
Chuck Soules |
FROM: |
Shoeb Uddin |
CC: |
David Corliss, David Cronin, Diane Stoddard, |
Date: |
May 20, 2008 |
RE: |
May 27, 2008 Agenda Item Set Bid Date – George Williams Way Street Construction project Project 14-CP4-407(BD), GWW, Project 15-CP5-407(BD), GWW, |
Please include the following item on the City Commission
agenda for consideration at the May 27, 2008 meeting:
Project Details:
The project includes the construction of George Williams Way from 6th
Street to the north city limits, including streets, sidewalks, multi-use paths,
storm sewer, and waterline improvements.
Plans and specifications for this project are complete and
the project is ready for bid letting.
All necessary right of way and easement documents have been
executed by the appropriate property owners.
Project Schedule:
This project is on schedule at this time. Construction will begin this
summer shortly after the contract is signed between the city and the lowest
responsible bidder. Depending on weather conditions, this project is expected
to be completed within about 9 months after starting construction.
Project Funding: The improvements are funded through benefit district financing with the city participating up to a maximum of $200,000.
Action
Request: Request approval from
the City Commission to set bid date of June 24, 2008 for City Bid No. B08055: Project No. 14-CP4-407(BD) - GWW,