CITY
OF LAWRENCE |
|
|
|
|
|
|
|
City Bid No. 08043 |
|
|
|
Project No. PW0808 |
|
|
|
2008 Overlay Program, Phase 1 |
|
|
|
Massachusetts Street,
6th to North Park; 7th St., Vermont to New York; & Kentucky St., 6th to
12th |
|
|
Bid Date: March 13,
2008 |
|
|
|
Engineer's Estimate: $512,762.50 |
|
|
|
|
LRM
Industries, Inc. |
Asphalt Improvement Co. |
ITEM |
DESCRIPTION |
UNITS |
QUANTITY |
UNIT PRICE |
AMOUNT |
UNIT PRICE |
AMOUNT |
1 |
Milling
(2") |
SY |
35,697 |
$ 1.25 |
$ 44,621.25 |
$ 1.70 |
$ 60,684.90 |
2 |
Asphaltic
Concrete Overlay Surface Course (2") |
TONS |
4,261 |
$
56.80 |
$ 242,024.80 |
$
56.00 |
$ 238,616.00 |
3 |
Asphaltic
Concrete Overlay Leveling Course |
TONS |
491 |
$
55.80 |
$ 27,397.80 |
$
56.00 |
$ 27,496.00 |
4 |
Full
Depth Pavement Patch * |
SY |
775 |
$
60.50 |
$ 46,887.50 |
$
65.00 |
$ 50,375.00 |
5 |
Crackfilling
up to 1" width* |
LF |
4,100 |
$ 0.55 |
$ 2,255.00 |
$ 0.60 |
$ 2,460.00 |
6 |
Manhole
Adjustment |
EACH |
9 |
$
450.00 |
$ 4,050.00 |
$
475.00 |
$ 4,275.00 |
7 |
Valve
Adjustment |
EACH |
97 |
$
130.00 |
$ 12,610.00 |
$
200.00 |
$ 19,400.00 |
8 |
Cold
Plastic Reflectorized Pavement Marking |
|
|
|
|
|
|
|
a) 4" Solid White Parking Space Line |
LF |
1,512 |
$ 2.60 |
$ 3,931.20 |
$ 2.55 |
$ 3,855.60 |
|
b) 6" Dotted White Extension Line |
LF |
176 |
$ 3.40 |
$ 598.40 |
$ 3.30 |
$ 580.80 |
|
c) 6" Broken White Lane Line |
LF |
850 |
$ 3.40 |
$ 2,890.00 |
$ 3.30 |
$ 2,805.00 |
|
d) 6" Solid White Channelization Line |
LF |
1,070 |
$ 3.40 |
$ 3,638.00 |
$ 3.30 |
$ 3,531.00 |
|
e) 24" Solid White Stop Line |
LF |
699 |
$
10.50 |
$ 7,339.50 |
$
10.30 |
$ 7,199.70 |
|
f) 36" Solid White Crosswalk Line |
LF |
844 |
$
12.50 |
$ 10,550.00 |
$
12.35 |
$ 10,423.40 |
|
g) Left Turn Lane Use Arrow |
EACH |
35 |
$
260.00 |
$ 9,100.00 |
$
255.00 |
$ 8,925.00 |
|
h) Right Turn Lane Use Arrow |
EACH |
10 |
$
260.00 |
$ 2,600.00 |
$
255.00 |
$ 2,550.00 |
|
i) Straight Through Lane Use Arrow |
EACH |
5 |
$
215.00 |
$ 1,075.00 |
$
210.00 |
$ 1,050.00 |
|
j) Left Turn and Through Lane Use Arrow |
EACH |
11 |
$
520.00 |
$ 5,720.00 |
$
515.00 |
$ 5,665.00 |
|
k) Right Turn and Through Lane Use Arrow |
EACH |
6 |
$
520.00 |
$ 3,120.00 |
$
515.00 |
$ 3,090.00 |
|
l) "ONLY" Word Marking |
EACH |
2 |
$
520.00 |
$ 1,040.00 |
515 |
$ 1,030.00 |
|
m) 4" Broken Yellow Lane Line |
LF |
600 |
$ 2.35 |
$ 1,410.00 |
2.3 |
$ 1,380.00 |
|
n) 4" Solid Yellow Lane Line |
LF |
2,272 |
$ 2.35 |
$ 5,339.20 |
2.3 |
$ 5,225.60 |
|
o) 4" Solid Double Yellow Lane Line ** |
LF |
2,785 |
$ 4.70 |
$ 13,089.50 |
4.65 |
$ 12,950.25 |
9 |
Heat
Fused Preformed Thermoplastic Pavement Marking |
|
|
|
|
|
|
|
a) 24" Solid White Stop Line |
LF |
3 |
$
26.15 |
$ 78.45 |
78 |
$ 234.00 |
10 |
Asphalt Test Core* |
EACH |
9 |
$
70.00 |
$ 630.00 |
70 |
$ 630.00 |
11 |
Traffic Control |
N/A |
1 |
Force Account |
$
40,000.00 |
Force Account |
$
40,000.00 |
|
|
Grand Total |
|
$ 491,995.60 |
|
$ 514,432.25 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|