CITY OF LAWRENCE, KANSAS |
|
|
|
|
|
|
|
PUBLIC WORKS DEPARTMENT |
|
|
CONSTRUCTION CONTRACT CHANGE ORDER |
|
|
|
|
|
Project Number and Name |
12-CP2-407(BD) |
|
|
|
|
25 th Terrace, O'Connell
Rd To Franklin Rd |
|
|
|
|
|
Change Order No |
4 |
|
Date |
4/30/2008 |
|
|
|
|
|
Contractor Name & Address |
Kings Constrruction |
|
|
|
|
P.O. Box 188 |
|
|
|
|
|
Oskaloosa, Ks. 66066 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
The
following changes are being made to the referenced construction contract:that
are not included in |
|
the
original unit price bid items: |
|
|
|
|
|
|
|
|
|
|
Item No. |
Description |
|
Units |
Unit
Cost |
Quantity (+/-) |
Net
Change in Contract Price ($) |
|
|
|
|
|
|
$0.00 |
|
|
|
|
|
|
$0.00 |
|
|
|
|
|
|
|
|
|
|
Changes
to original unit price bid items are as follows: |
|
|
|
|
|
Item No. |
Description |
|
Units |
Unit Cost |
Quantity (+/-) |
Net Change in
Contract Price ($) |
|
|
36 |
4" Edge Drain |
|
L.F |
$10.25 |
660 |
$6,765.00 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Original Contract Amount |
|
$1,457,591.30 |
|
|
Net Change by Previous
Change Order(s) |
|
$43,963.18 |
|
|
Net Change by This Change
Order |
|
$6,765.00 |
|
|
New Contract Amount |
|
$1,508,319.48 |
|
|
|
|
Original Contract Time or
Completion Date |
|
110 |
|
|
Net Change by Previous
Change Order(s) |
|
0 |
|
|
Net Change by This Change
Order |
|
0 |
|
|
New Contract Time or
Completion Date |
|
110 |
|
|
|
|
|
|
Approved By: |
|
|
|
|
|
|
|
Date: |
|
|
|
Contractor |
|
|
|
|
|
|
Date: |
|
|
|
Asst Dir of Public Works |
|
|
|
|
|
|
|
|
|
|
|