CITY OF LAWRENCE, KANSAS |
|
|
|
|
|
|
|
PUBLIC WORKS DEPARTMENT |
|
|
CONSTRUCTION CONTRACT CHANGE ORDER |
|
|
|
|
|
Project Number and Name |
12-CP2-407(BD) |
|
|
|
|
25 th Terrace, O'Connell
Rd To Franklin Rd |
|
|
|
|
|
Change Order No |
2 |
|
Date |
3/25/2008 |
|
|
|
|
|
Contractor Name & Address |
Kings Constrruction |
|
|
|
|
P.O. Box 188 |
|
|
|
|
|
Oskaloosa, Ks. 66066 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
The
following changes are being made to the referenced construction contract:that
are not included in |
|
the
original unit price bid items: |
|
|
|
|
|
|
|
|
|
|
Item No. |
Description |
|
Units |
Unit
Cost |
Quantity (+/-) |
Net
Change in Contract Price ($) |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Changes
to original unit price bid items are as follows: |
|
|
|
|
|
Item No. |
Description |
|
Units |
Unit Cost |
Quantity (+/-) |
Net Change in
Contract Price ($) |
|
|
22 |
2" Asphaltic Concrete Surface Course |
Tons |
$46.25 |
-49.5 |
-$2,289.38 |
|
|
24 |
6" Asphalt Base
Course |
|
Tons |
$43.00 |
-176 |
-$7,568.00 |
|
37 |
Combined Curb and
Gutter |
|
LF |
$13.85 |
-173 |
-$2,396.05 |
|
33 |
5x4 Concrete Sidewalk |
S.Y |
$25.00 |
-76.89 |
-$1,922.25 |
|
28 |
Fly Ash Treated Subgrade |
S.Y |
$3.85 |
-557.44 |
-$2,146.14 |
|
68 |
8" Ductile Iron Pipe Waterline and Fittings |
L.F |
$29.00 |
-180 |
-$5,220.00 |
|
|
|
|
|
|
|
Original Contract Amount |
|
$1,457,591.30 |
|
|
Net Change by Previous
Change Order(s) |
|
$27,643.00 |
|
|
Net Change by This Change
Order |
|
-$21,541.82 |
|
|
New Contract Amount |
|
$1,463,692.48 |
|
|
|
|
Original Contract Time or
Completion Date |
|
110 |
|
|
Net Change by Previous
Change Order(s) |
|
0 |
|
|
Net Change by This Change
Order |
|
0 |
|
|
New Contract Time or
Completion Date |
|
110 |
|
|
|
|
|
|
Approved By: |
|
|
|
|
|
|
|
Date: |
|
|
|
Contractor |
|
|
|
|
|
|
Date: |
|
|
|