Downtown Pavement Maintenance Project

2008 Mill & Overlay

Meeting with Downtown Lawrence Inc.

7:30 AM, April 9, 2008

 

 

Project - Mill & Overlay

·        Massachusetts – 6th to North Park

·        Kentucky – 6th to 12th

·        7th StVermont to New York

·        Alternate Section (if funds are available)- Kentucky- 12th to 19th

 

General Goals for Paving Projects

·        Most economical process possible

·        Best finished product possible (smooth, min. no. joints)

·        Minimize construction schedule

·        Minimize impacts on traffic and adjacent properties

 

Potential Implications of Increased Restrictions

·        Higher costs with lost efficiency

·        Lower quality of finished product if done piecemeal (rougher, more joints)

·        Longer construction schedule

·        May or may not minimize impacts on traffic and adjacent properties

·        Lack of interest by contractors

 

Proposed Approach for Massachusetts

·        Milling of entire length can occur under traffic

o       Some obstructions from parked cars could slow down progress

·        Close 2-3 block segments at a time for patching and paving

o       Cross streets will be closed except 9th – no work through the 9th St intersection i.e. if 6th to 8th or 9th is closed, then 7th and/or 8th will be closed at each edge of Mass

o       Perform all patching and then paving

o       Reopen segment

·        Move to next 2-3 block segment

·        Concrete collars around manholes and water valves in pavement will be done after paving is complete. Contractor will provide traffic control to minimize traffic impacts.

·        Similar approach is suggested for paving 7th St and Kentucky

·        No closure of Kentucky or 7th St. while any segment of Mass is closed. Some work may be allowed on Kentucky and 7th as long as traffic is not significantly impeded

 

 

 

Approximate Time Required

·        Milling & cleanup – 2-3 days

·        Closure for each segment – 3-4 days depending on amount of patching required

·        Total Time on Mass (if closures allowed) - 12-15 days

·        Contractor will be required to work continuously on Mass until complete

(Remember – Construction is weather dependent. We will try to avoid starting work when weather forecasts indicate completion may delayed for several days)

 

Project Schedule Assumptions/Questions

·        Work on Mass must be completed before Sidewalk Sale (July 17)

·        Will contractor be permitted to work on weekends- Sat and/or Sun?

·        Are there other scheduled events in the downtown area that need to be considered?

·        Need to have contract awarded and ready to start by June 1 to provide adequate “contingency” in the schedule for weather impacts and still meet July 17 date