PC Minutes
ITEM NO. 5
PDP-01-01-08: Preliminary
Development Plan for Pine Ridge Plaza Addition Lot 1B, located at 3235 Ousdahl.
The plan proposes the construction of a 37,550 sq. ft. commercial
office/warehouse building on approximately 3.099 acres. Submitted by Grob
Engineering, for Western Extralite Company/Fraternal Investors, LLC, property
owner of record.
STAFF
PRESENTATION
Sandra Day presented the item.
APPLICANT PRESENTATION
Dean Grob, Grob Engineering Services,
agreed with the staff report and were still discussing the truck traffic.
Commission Lawson inquired about the
purpose of separating the traffic in the parking area.
Mr. Grob said they receive semi trailer
deliveries so circular turning would be difficult.
PUBLIC
HEARING
No public comment.
ACTION TAKEN
Motioned by Commissioner Finkeldei,
seconded by Commissioner Harris, to approve the Preliminary Development Plan
based upon the findings of fact presented in the body of the Staff Report and
forwarding it to the City Commission with a recommendation for approval subject
to the following conditions:
1.
Approval
of the following waivers and reductions:
a.
Yard
reductions along the west side to 12 feet rear yard setback;
b.
Yard
reductions along the east side to 15 feet front/peripheral yard setback;
c.
Yard
reductions along the south side to 15’ peripheral yard setback for the parking
lot;
d.
Off-street
parking from 131 spaces to 90 spaces.
Unanimously
approved 7-0. (Commissioner Hird left the meeting prior to the vote)