Memorandum

City of Lawrence

Utilities

 

TO:

 

David Corliss – City Manager

Cynthia Boecker, Assistant City Manager

Diane Stoddard, Assistant City Manager

FROM:

David E. Cox – Assistant Director Utilities - Operations

CC:

Dave Wagner – Director of Utilities

Alan Landis – Purchasing

Carolyn Woodhead – Residuals Coordinator

Date:

February 29, 2008

RE:

Change Order for the Lime Residuals removal contract to RD Johnson at Clinton Water Treatment Plant

 

Please include the following item on the City Commission agenda for consideration at the March 11, 2008 meeting:

 

Request approval to increase authorization from $120,000 to $170,000 for the removal of an additional 10,257 CY of lime residuals.

 

Project Background 

On January 2, 2008, purchase order #068412 was awarded to RD Johnson in the amount of $120,000 to remove lime residuals at the Clinton Water Treatment Plant. This most recent purchase order was amendment number 1 to the original contract dated October 26, 2006 to RD Johnson for lime residuals removal at the Wastewater Treatment plant on East 8th street.  Amendment #1 has been utilized in full to remove approximately 10,077 CY or residuals. The projected amount of funding was not sufficient to remove all the residuals in place.  Another 10,257 CY has been calculated to be removed from the lagoon.

 

Project Status/ Details 

RD Johnson is currently a subcontractor also working on the Clinton Water Plant expansion. RD Johnson’s equipment and staff are on site and have completed removal of the original contracted amount of lime residuals. Approximately 10,257 CY of lime residuals remain to be removed. If this extra work was bid out separately it would cost more money due to additional remobilization and timing of the work.  Construction work is slow at this time of year which benefits the city in gaining a reduced cost for the additional lime residuals removal as a change order.  In addition, the City has agreed to allow additional soil spoils that were removed by RD Johnson from the plant expansion to be retained on site in the event they can be used to stabilize the western side of the plant’s process site or be used off site as additional fill material.

 

Project Funding

Funding for this project is through the Utilities operating budget.

  

Action Request

Authorization to increase the existing Lime residuals contract to RD Johnson from $120,000 to $170,000.