Ohio St, 6th st. to 8th st.

Brick Street Reconstruction

PROJECT INFORMATION SHEET

UPDATED: February 27, 2008

 

Project Scope  

Reconstruction of Ohio St. between 6th St. and 8th St. back to a Brick Street.

 

Project Funding

KDOT Transportation Enhancement Program Project

  • Rehabilitation of historic transportation facility (Old West Lawrence)
  • Selected by KDOT in 2005 to be funded for construction in 2008
  • Funding is 80%/20% (KDOT/City)
  • Est. Cost $670,000 ($536,000/$134,000)

 

Project Timeline

  • Utility relocation and storm sewer replacement at 7th & Ohio St. (February/March 2008)
  • Pre-construction meeting with neighborhood (March 2008)
  • Begin Construction (April 2008)
  • Two Stages of Construction (approx. 6 months total)
    • 6th to 7th St.
    • 7th to 8th St.
  • End Construction (Late Summer/Early Fall 2008)

 

Construction Details

  • Remove existing asphalt overlay
  • Remove and salvage existing layers of brick (under current asphalt)
  • Construct new roadway with concrete base and reused brick
  • Remove, clean, and replace existing stone curbing and hitching posts

 

Goals

  • Construct a long lasting roadway
  • Provide an aesthetically pleasing street to neighborhood
  • Enhance the historical appeal of Lawrence