Memorandum

City of Lawrence

City Manager’s Office

 

TO:

Mayor and City Commissioners

 

FROM:

David L. Corliss, City Manager

 

CC:

Dave Wagner, Director of Utilities

 

Date:

February 25, 2008

 

RE:

Wastewater Utility Improvements and plans for the future

 

 

The purpose of this memorandum is to discuss a proposed 2008 Wastewater Facilities Master Plan, the initial capacity and timing of the Wakarusa Water Reclamation Facility (WWRF), and improvements at the Four Seasons Pump Station.  The memorandum also discusses delivery method (design-bid-build, design-build, construction management, etc.). 

 

Based on the recommendations of the 2003-2008 Wastewater Master Plan, the City has made a significant investment in our water and wastewater infrastructure. This Master Plan has served its useful life and been the basis for the City’s Capital Improvement Program for over four years but is based on a limited amount of technical data that is now over six years old. In addition to completion of numerous construction projects, actual population growth rates have fallen below the assumptions used in the Master Plan. Rather than just studying the initial capacity and timing of the WWRF, a new Facilities Plan should be prepared to quickly answer the question of WWRF capacity/timing and provide a new Capital Improvement Program based on a new system model.

 

Infrastructure Investment

Beginning with the adoption of the 2003 Wastewater Master Plan the Department implemented a schedule of Capital Improvement Projects (CIP) designed to replace and rehabilitate aged infrastructure, and increase the capacities of existing facilities to accommodate growth. The Department has also taken the lead, or participated in, constructing facilities designed to extend the sanitary sewer system to areas of growth; most notably to the northwest and southeast of the City.

 

With the implementation of the CIP schedule, the Department has completed over $11 million dollars worth of projects including; the reconstruction and expansion of three (3) North Lawrence Pump Stations, the expansion and rehabilitation of Pump Station 16 (6th and Kentucky) from 8.0MGD to 18.0MGD, the installation of approximately 6,000 linear feet of gravity relief interceptor in the Yankee Tank Creek Basin, the installation and rehabilitation of over 4,000 linear feet of gravity sewer in the Alvamar Area, the replacement of aged sanitary sewers in the 6th & Indiana, 17th & Massachusetts and 14th & New Hampshire areas, and the abandonment of Pump Stations 26 and 33 and the redirection of their flows to nearby gravity sewers. The Department has also completed approximately $3.5 million dollars worth of in situ rehabilitation of over 1,500 manholes and 68,000 linear feet of gravity sewer pipe. Department Staff have also implemented measures to increase the reliability and efficiency of existing infrastructure. For example, staff constructed and installed new PLC (Programmable Logic Controller) control systems at all sanitary sewer pump stations.

 

The Department of Utilities, in response to the Northwest Area Update, accelerated the construction of Pump Station PS48 along with its forcemain and gravity interceptor. This $12 million dollar facility was designed and constructed to alleviate current sanitary sewer capacity issues in the Northwest area of the City, as well as provide for the future development of the area. In response to this same study the Department also implemented the installation of larger capacity pumps in Pump Station PS44. The Department is currently participating in the Douglas County Southeast Area Sanitary Sewer Benefit District. These facilities, including a new regional Pump Station PS49, will provide sanitary sewer capacity to the area southeast of 23rd Street and O’Connell Road.

 

The Department continues to implement needed projects including the expansion of Pump Station PS25 in the East Hills Business Park area, the construction of the West Baldwin Creek Interceptor, the replacement and rehabilitation of gravity sewers in the 8th & Michigan area, and the permanent flow metering program.

 

Technical Data Comparison

The proposed 2008 Wastewater Facilities Master Plan will be based on improved and more detailed system and flow information than any previous system evaluation. Over the last several years, the department initiated efforts using the latest technologies to enhance critical system data acquisition and information accuracy specifically for this purpose.

 

In October of 2006, twenty-seven permanent flow meters, four portable flow meters, and thirteen rain gauges were installed through the collection system. These devices are providing remote, continuous data collection of system flows and rainfall. These meters and gauges are distributed throughout the system and provide for complete and comprehensive information about system capacity and performance, not just system wide, but for each basin. See the attached maps for a visual comparison of the location, and numbers, of meters between the 2003 evaluation and the proposed 2008 evaluation. The data used in 2003 was collected over the spring of 2000 and represented a sampling of only a few areas. The areas sampled and the resulting analysis assumed the worst-case infrastructure condition. The resulting flow parameters were then applied system wide.

 

Using the latest global positioning systems (GPS) and equipment staff have acquired extremely accurate information about the collection system configuration, including determining actual installed slopes of gravity sewers. The system information includes the entirety of the public system. The system evaluation effort performed in 2000 (that was the basis of the 2003 plan) evaluated only the major lines accounting for about 24% of the system. The currently proposed study will evaluate all of the system. See the attached chart of pipe sizes.

 

A summary table representing those differences follows:

 

 


Data for Current and Future Master Plans

 

Data Collected in 2000

Data currently available -2008

RAIN AND FLOW DATA

Number of meters

7

32

Number of rain gauges

4

13

Total days monitored

70

> 510

Period evaluated

April-June 2000

Oct 06 - Current

Number of data points

45,000

>2,000,000

Basins evaluated independently

4

25 (all)

 

 

 

COLLECTION SYSTEM DATA

Collection system liner feet

1,886,000

2,097,000

Collection system liner feet modeled

464,000

2,089,000

% of system to evaluate

25%

100%

System configuration assumptions made

Yes

No

 

 

These flow metering and GPS efforts in combination provide a level of detailed information far beyond what was used in the 2003 Master Plan. This level of information will allow for a more efficient and accurate determination of system capacity and maintenance problems. This data will also be an asset in the development of a very accurate capital improvement program now and in the future. 

 

Population Growth Rates

The Master Plan used population growths rates that ranged from 2.0% to 2.7% to predict the population from 2000 to 2050.  The average population growth rate from 2000 to 2007 has been 1.66% compared to the Master Plan estimate of 2.2% for the same period. However, since 2005, the average growth rate has been less than 1.0%. As indicated in previous memos, with an average population growth rate of 1% the City’s population will not exceed 100,000 until 2017 as opposed to 2010 as projected by the Master Plan.  The growth rates for the proposed Facilities Plan will have to factor in the recent economic slow down in order to provide an accurate forecast of future utility needs for the city.

 

Wakarusa Water Reclamation Facility

The Master Plan demonstrated the need for the WWRF. However, the difference in growth rates noted above may have an impact on the initial size and timing of construction of the WWRF. With the flow data and system asset information that is available, once a model is completed and growth projections set, it will be relatively easy to look at initial capacity and timing of the improvements for the WWRF. If the recommendation is either to begin construction immediately or to delay construction to a future date, the City is well positioned for the construction of the WWRF, with land acquisition, land use approvals and regulatory approvals in place.  We have the ability to proceed to final design and construction for this facility at the appropriate time.

 

Four Seasons Pump Station

While a new Master Plan is being prepared, there are immediate improvements needed at the Four Seasons Pump Station facility, generally located west of Kasold near 31st Street. The improvements recommended in the Master Plan for the facility are critical to resolve ongoing operational issues/concerns in the collection system along 31st Street. The recent approval of new development along the 31st Street corridor only adds to the need for the improvements to be installed in a timely manner.

 

Delivery Methods:  Design/Build and Design-Bid-Build

 

City Commission direction on the delivery method for these important projects is desired. The selection of a delivery method for public infrastructure involves a number of important public policy issues and priorities. Typically, the City has followed the Design-Bid-Build system, whereby the City selects a design engineer to provide a full design of the project, the project is publicly bid, and the bid is awarded to the lowest responsible bidder.  This system places a high value on the competitive bidding process to provide evidence that public funds are appropriately spent and allocated.  The separation of responsibilities between the design consultant and the contractor is also viewed as a positive check on roles, although advocates for design-build point out that it can create unnecessary and costly situations in the execution of a quality and timely project. Advocates of design-build highlight the value of timely production of the public infrastructure because certain phases of a project can be initiated without the necessity of complete construction documents.  In fact, the cooperation between the design consultant and the contractor is viewed as a positive factor in reducing both time and cost in a public project.  Design-build typically includes portions of a project which are not competitively bid but instead self-performed by the design-build contractor.  The Design-Build team presents a guaranteed maximum price (GPM) which includes both bid and non-bid items.  A difficulty with a GPM from the Design-Build team can occur if the proposed price is not acceptable to the owner, or if there is a concern in publicly justifying non-bid portions of a GPM. 

 

We have successfully used Design-Build when the importance of producing a timely infrastructure improvement was a significant factor and plan to recommend this method in the future in appropriate situations. We further recommend that our purchasing policy and ordinances be amended to better reflect this delivery method for construction projects.

 

Commission discussion and direction on this issue is desired. To some extent, the selection of a delivery method is based on the weighing of the importance of competitively bidding all portions of a project versus the potential for value savings and time savings with a combination of the design consultant and the contractor.  Either method can be effectively used by the community and will be efficiently and effectively implemented by City staff. 

 

Recommendations

With changes in community growth patterns and projections, the completion of construction projects identified above and with new and more comprehensive technical system data, staff recommends preparing a new 2008 Wastewater Facilities Master Plan. The new Facilities Plan will review the timing and scope of the WWRF; provide a model of the entire wastewater system using the enhanced system data and update of the Capital Improvement Program based on the new model information. Staff also recommends proceeding with the improvements to the storage capacity at Four Seasons Pump Station.

 

  • Advertise an RFP for Professional Engineering Services for a Wastewater Facilities Master Plan

 

  • Advertise an RFP for Professional Engineering Services for Design-Bid-Build of the Fours Seasons Pump Station Improvements.