City of
Public Works
Department
MEMORANDUM
DATE: February 13, 2008
TO: David L. Corliss
City Manager
FROM: Dena E.
Mezger, P.E.
Assistant Director of Public
Works
On February
12, 2008 the City of
City Bid No. B08001
K-10 & O’Connell Road
Project 45-GI5-905(BD),
Eastbound Right Turn Lane, Geometric & Waterline Improvements
Project
35-GI1-704(BD), Westbound Left Turn Lane,
VENDOR |
TOTAL
BID |
Engineer’s
Estimate |
$304,355.00 |
LRM Industries, Inc. |
$336,396.70 |
R. D. Johnson Excavating |
$362,879.98 |
In
comparing the bids with the engineer’s estimate the significant differences
were in the earthwork prices. The engineer’s estimate was based on average bid
prices from recent projects. However, those averages were from projects with
large quantities of earthwork. The much smaller quantities of earthwork and the
physically restricted work area in this project resulted in higher unit prices
than the averages. The higher unit prices are reasonable for the work involved
and the overall bid amount is still well below the original benefit district project
estimate of approximately $700,000 for construction.
Recommendation Action:
Waive engineer’s estimate and approve bid from LRM
Industries, Inc. for Projects 45-GI5-905(BD) and 35-GI1-704(BD) in the amount
of $336,396.70 provided the contractor can meet the terms established in the
contract documents.
Attachment: Bid
Tab
cc: Cynthia Boecker
Diane Stoddard
Chuck Soules
Bobbie Walthall
Alan Landis
Tammy Bennett