CITY OF LAWRENCE, KANSAS
PUBLIC WORKS DEPARTMENT
CONSTRUCTION CONTRACT CHANGE ORDER
Project Number and Name  10-SR5-307 ( C)  
2007 Overlay and Curb Repair, Phase 2
Change Order No 1 (Final) Date 12/5/2007
Contractor Name & Address LRM Industries, Inc.  
P.O Box 4150    
Lawrence, KS 66046  
       
The following changes are being made to the referenced construction contract:that are not included in 
the original unit price bid items:
             
Item No. Description   Units Unit Cost Quantity  (+/-) Net Change in Contract Price ($)
6 6" Reinforced Conc Pavt - revise unit price by $1.25 to add high-early strength matl.   SY $2.25 1,314.00 $2,956.50
9 24" Conc C&G - reduce unit price by $0.06 to eliminate portion of joint sealant   LF -$0.06 11,600.00 -$696.00
10 30" Conc C&G - reduce unit price by $0.06 to eliminate portion of joint sealant   LF -$0.06 10,390.00 -$623.40
27 Addtl milling @ 23rd & Mass for Street Div project   SY $2.90 384.00 $1,113.60
28 6" Dia. PVC Underdrain w/filter fabric sock   LF $7.20 350.00 $2,520.00
29 Remove & haul asphalt on conc base left below depth of milling   LS $2,096.38 1.00 $2,096.38
  Subtotal         $7,367.08
Changes to original unit price bid items are as follows:
Item No. Description   Units Unit Cost Quantity  (+/-) Net Change in Contract Price ($)
1 Milling (2")   SY $1.25 3983 $4,978.75
2 Asphlatic Conc Surface Course   Tons $42.95 762.89 $32,766.13
3 Asphaltic Conc. Leveling Course   Tons $51.60 131.13 $6,766.31
4 Asphalt Conc Patch (Full-depth)   Tons $99.50 130.01 $12,936.00
5 Conc Pavement Patch (Full-dpeth)   SY $74.35 562.65 $41,833.03
6 6" Reinforced Conc Pavement   SY $46.20 -531.22 -$24,542.36
7 8" Reinforced Conc Pavement   SY $54.90 48.99 $2,689.55
8 10" Conc Pavt w/integral curb & ramps SY $83.80 15.61 $1,308.12
9 24" Conc Curb & Gutter   LF $18.69 202 $3,775.38
10 30" Conc Curb & Gutter   LF $20.74 -460 -$9,540.40
11 4" Conc Sidewalk   SY $37.85 15.53 $587.81
12 Conc Access Ramp   EA $575.00 2 $1,150.00
16 Driveway Wedge   SY $10.50 -289 -$3,034.50
17 Crackfilling          
  a) up to 1" width   LF $0.50 -4741 -$2,370.50
  b) greater than 1" width   LF $0.50 -840 -$420.00
19 Valve Adjustment   EA $205.00 7 $1,435.00
22 Traffic Signal Loop   EA $1,260.00 3 $3,780.00
23 Asphalt Test Core   EA $70.50 -4 -$282.00
24 Temporary Surfacing   Tons $19.15 -65 -$1,244.75
26 Traffic Control   Force Acct $3,364.55 1 $3,364.55
  Subtotal         $75,936.10
Original Contract Amount $1,110,652.60
Net Change by Previous Change Order(s) $0.00
Net Change by This Change Order $83,303.18
New Contract Amount $1,193,955.78
Original Contract Time or Completion Date 60 working days
Net Change by Previous Change Order(s) 0
Net Change by This Change Order 10 working days
New Contract Time or Completion Date 70 working days
Approved By:
    Date:  
Contractor
    Date:  
Asst Dir of Public Works