CITY OF LAWRENCE, KANSAS |
|
|
|
|
|
|
|
PUBLIC WORKS DEPARTMENT |
|
|
CONSTRUCTION CONTRACT CHANGE ORDER |
|
|
|
|
|
Project Number and Name |
10-SR5-307 ( C) |
|
|
|
|
2007 Overlay and Curb
Repair, Phase 2 |
|
|
|
|
|
Change Order No |
1 |
(Final) |
Date |
12/5/2007 |
|
|
|
|
|
Contractor Name & Address |
LRM Industries, Inc. |
|
|
|
|
P.O Box 4150 |
|
|
|
|
|
Lawrence, KS 66046 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
The
following changes are being made to the referenced construction contract:that
are not included in |
|
the
original unit price bid items: |
|
|
|
|
|
|
|
|
|
|
Item No. |
Description |
|
Units |
Unit
Cost |
Quantity (+/-) |
Net
Change in Contract Price ($) |
|
6 |
6"
Reinforced Conc Pavt - revise unit price by $1.25 to add high-early strength
matl. |
|
SY |
$2.25 |
1,314.00 |
$2,956.50 |
|
9 |
24" Conc
C&G - reduce unit price by $0.06 to eliminate portion of joint sealant |
|
LF |
-$0.06 |
11,600.00 |
-$696.00 |
|
10 |
30" Conc
C&G - reduce unit price by $0.06 to eliminate portion of joint sealant |
|
LF |
-$0.06 |
10,390.00 |
-$623.40 |
|
27 |
Addtl milling @
23rd & Mass for Street Div project |
|
SY |
$2.90 |
384.00 |
$1,113.60 |
|
28 |
6" Dia. PVC
Underdrain w/filter fabric sock |
|
LF |
$7.20 |
350.00 |
$2,520.00 |
|
29 |
Remove &
haul asphalt on conc base left below depth of milling |
|
LS |
$2,096.38 |
1.00 |
$2,096.38 |
|
|
Subtotal |
|
|
|
|
$7,367.08 |
|
|
|
Changes
to original unit price bid items are as follows: |
|
|
|
|
|
Item No. |
Description |
|
Units |
Unit Cost |
Quantity (+/-) |
Net Change in
Contract Price ($) |
|
|
1 |
Milling (2") |
|
SY |
$1.25 |
3983 |
$4,978.75 |
|
2 |
Asphlatic Conc
Surface Course |
|
Tons |
$42.95 |
762.89 |
$32,766.13 |
|
3 |
Asphaltic Conc. Leveling Course |
|
Tons |
$51.60 |
131.13 |
$6,766.31 |
|
4 |
Asphalt Conc Patch
(Full-depth) |
|
Tons |
$99.50 |
130.01 |
$12,936.00 |
|
5 |
Conc Pavement Patch
(Full-dpeth) |
|
SY |
$74.35 |
562.65 |
$41,833.03 |
|
6 |
6" Reinforced
Conc Pavement |
|
SY |
$46.20 |
-531.22 |
-$24,542.36 |
|
7 |
8" Reinforced
Conc Pavement |
|
SY |
$54.90 |
48.99 |
$2,689.55 |
|
8 |
10"
Conc Pavt w/integral curb & ramps |
SY |
$83.80 |
15.61 |
$1,308.12 |
|
9 |
24" Conc Curb
& Gutter |
|
LF |
$18.69 |
202 |
$3,775.38 |
|
10 |
30" Conc Curb
& Gutter |
|
LF |
$20.74 |
-460 |
-$9,540.40 |
|
11 |
4" Conc Sidewalk |
|
SY |
$37.85 |
15.53 |
$587.81 |
|
12 |
Conc Access Ramp |
|
EA |
$575.00 |
2 |
$1,150.00 |
|
16 |
Driveway Wedge |
|
SY |
$10.50 |
-289 |
-$3,034.50 |
|
17 |
Crackfilling |
|
|
|
|
|
|
|
a) up to 1"
width |
|
LF |
$0.50 |
-4741 |
-$2,370.50 |
|
|
b) greater than
1" width |
|
LF |
$0.50 |
-840 |
-$420.00 |
|
19 |
Valve Adjustment |
|
EA |
$205.00 |
7 |
$1,435.00 |
|
22 |
Traffic Signal Loop |
|
EA |
$1,260.00 |
3 |
$3,780.00 |
|
23 |
Asphalt Test Core |
|
EA |
$70.50 |
-4 |
-$282.00 |
|
24 |
Temporary Surfacing |
|
Tons |
$19.15 |
-65 |
-$1,244.75 |
|
26 |
Traffic Control |
|
Force Acct |
$3,364.55 |
1 |
$3,364.55 |
|
|
Subtotal |
|
|
|
|
$75,936.10 |
|
|
|
|
|
|
Original Contract Amount |
|
$1,110,652.60 |
|
|
Net Change by Previous
Change Order(s) |
|
$0.00 |
|
|
Net Change by This Change
Order |
|
$83,303.18 |
|
|
New Contract Amount |
|
$1,193,955.78 |
|
|
|
|
Original Contract Time or
Completion Date |
|
60 working days |
|
|
Net Change by Previous
Change Order(s) |
|
0 |
|
|
Net Change by This Change
Order |
|
10 working days |
|
|
New Contract Time or
Completion Date |
|
70 working days |
|
|
|
|
|
|
Approved By: |
|
|
|
|
|
|
|
Date: |
|
|
|
Contractor |
|
|
|
|
|
|
Date: |
|
|
|
Asst Dir of Public Works |
|
|
|
|
|
|
|
|
|
|
|