| CITY OF LAWRENCE, KANSAS | |||||||||
| PUBLIC WORKS DEPARTMENT | |||||||||
| CONSTRUCTION CONTRACT CHANGE ORDER | |||||||||
| Project Number and Name | 10-SR5-307 ( C) | ||||||||
| 2007 Overlay and Curb Repair, Phase 2 | |||||||||
| Change Order No | 1 | (Final) | Date | 12/5/2007 | |||||
| Contractor Name & Address | LRM Industries, Inc. | ||||||||
| P.O Box 4150 | |||||||||
| Lawrence, KS 66046 | |||||||||
| The following changes are being made to the referenced construction contract:that are not included in | |||||||||
| the original unit price bid items: | |||||||||
| Item No. | Description | Units | Unit Cost | Quantity (+/-) | Net Change in Contract Price ($) | ||||
| 6 | 6" Reinforced Conc Pavt - revise unit price by $1.25 to add high-early strength matl. | SY | $2.25 | 1,314.00 | $2,956.50 | ||||
| 9 | 24" Conc C&G - reduce unit price by $0.06 to eliminate portion of joint sealant | LF | -$0.06 | 11,600.00 | -$696.00 | ||||
| 10 | 30" Conc C&G - reduce unit price by $0.06 to eliminate portion of joint sealant | LF | -$0.06 | 10,390.00 | -$623.40 | ||||
| 27 | Addtl milling @ 23rd & Mass for Street Div project | SY | $2.90 | 384.00 | $1,113.60 | ||||
| 28 | 6" Dia. PVC Underdrain w/filter fabric sock | LF | $7.20 | 350.00 | $2,520.00 | ||||
| 29 | Remove & haul asphalt on conc base left below depth of milling | LS | $2,096.38 | 1.00 | $2,096.38 | ||||
| Subtotal | $7,367.08 | ||||||||
| Changes to original unit price bid items are as follows: | |||||||||
| Item No. | Description | Units | Unit Cost | Quantity (+/-) | Net Change in Contract Price ($) | ||||
| 1 | Milling (2") | SY | $1.25 | 3983 | $4,978.75 | ||||
| 2 | Asphlatic Conc Surface Course | Tons | $42.95 | 762.89 | $32,766.13 | ||||
| 3 | Asphaltic Conc. Leveling Course | Tons | $51.60 | 131.13 | $6,766.31 | ||||
| 4 | Asphalt Conc Patch (Full-depth) | Tons | $99.50 | 130.01 | $12,936.00 | ||||
| 5 | Conc Pavement Patch (Full-dpeth) | SY | $74.35 | 562.65 | $41,833.03 | ||||
| 6 | 6" Reinforced Conc Pavement | SY | $46.20 | -531.22 | -$24,542.36 | ||||
| 7 | 8" Reinforced Conc Pavement | SY | $54.90 | 48.99 | $2,689.55 | ||||
| 8 | 10" Conc Pavt w/integral curb & ramps | SY | $83.80 | 15.61 | $1,308.12 | ||||
| 9 | 24" Conc Curb & Gutter | LF | $18.69 | 202 | $3,775.38 | ||||
| 10 | 30" Conc Curb & Gutter | LF | $20.74 | -460 | -$9,540.40 | ||||
| 11 | 4" Conc Sidewalk | SY | $37.85 | 15.53 | $587.81 | ||||
| 12 | Conc Access Ramp | EA | $575.00 | 2 | $1,150.00 | ||||
| 16 | Driveway Wedge | SY | $10.50 | -289 | -$3,034.50 | ||||
| 17 | Crackfilling | ||||||||
| a) up to 1" width | LF | $0.50 | -4741 | -$2,370.50 | |||||
| b) greater than 1" width | LF | $0.50 | -840 | -$420.00 | |||||
| 19 | Valve Adjustment | EA | $205.00 | 7 | $1,435.00 | ||||
| 22 | Traffic Signal Loop | EA | $1,260.00 | 3 | $3,780.00 | ||||
| 23 | Asphalt Test Core | EA | $70.50 | -4 | -$282.00 | ||||
| 24 | Temporary Surfacing | Tons | $19.15 | -65 | -$1,244.75 | ||||
| 26 | Traffic Control | Force Acct | $3,364.55 | 1 | $3,364.55 | ||||
| Subtotal | $75,936.10 | ||||||||
| Original Contract Amount | $1,110,652.60 | ||||||||
| Net Change by Previous Change Order(s) | $0.00 | ||||||||
| Net Change by This Change Order | $83,303.18 | ||||||||
| New Contract Amount | $1,193,955.78 | ||||||||
| Original Contract Time or Completion Date | 60 working days | ||||||||
| Net Change by Previous Change Order(s) | 0 | ||||||||
| Net Change by This Change Order | 10 working days | ||||||||
| New Contract Time or Completion Date | 70 working days | ||||||||
| Approved By: | |||||||||
| Date: | |||||||||
| Contractor | |||||||||
| Date: | |||||||||
| Asst Dir of Public Works | |||||||||