City of Lawrence |
Finance Department |
|
MEMORANDUM |
DATE: |
November 7, 2007 |
|
|
TO: |
David Corliss |
|
City Manager |
|
|
FROM: |
Alan D. Landis |
|
Purchasing Specialist |
EQUIPMENT BUILDING AT THE WASTEWATER TREATMENT PLANT
UTILITIES DEPARTMENT – #B07064
Utilities Department requested bids for construction of an equipment building at the Wastewater Treatment Plant. It will be used for storing equipment such as generators, trucks, and loaders when not in use. It was recommended by the Central Maintenance Garage Superintendent to store this equipment in an enclosed area. This purchase was budgeted in the 2007 budgeting process.
VENDOR |
TOTAL BID |
BA Green |
$125,629.00 |
Penny Construction |
136,350.00 |
GSR Construction |
163,800.00 |
Recommendation Action:
Approve bid from BA Green for construction of an equipment building in the amount of $125,629.00. (Utilities/Water Treatment & Collection Systems)
cc: |
Cynthia Boecker |
Dave Wagner |
|
Diane Stoddard |
Dave King |
|
Frank Reeb |
Mike Ellis |
|
Bobbie Walthall |
Jonathan Douglas |
|
Diane Trybom |
|