Memorandum
City of Lawrence
Department of Public Works
TO: |
David L. Corliss, Cynthia Boecker, Diane Stoddard |
FROM: |
Chuck Soules |
CC: |
John Miller, Scott Wagner, Dena Mezger, Shoeb Uddin |
Date: |
October 9, 2007 |
RE: |
October 23 , 2007 Agenda Item Maximum Assessment Hearing Stoneridge Drive, Overland Drive to 6th Street, Project No. 25-CP8-806(BD) Overland Drive, Queens Road to Stoneridge Drive, Project No. 19-CP6-506(BD) |
Please include the following item on the City Commission consent agenda for consideration at the October 23, 2007 meeting:
Project Description. The improvements include the construction of Stoneridge north of 6th Street to Overland Drive, and Overland Drive from Stoneridge to Queens Road. A signal will be installed at 6th Street with a dedicated right-turn lane from 6th Street onto Stoneridge Drive. A roundabout will be constructed at the intersection of Stoneridge Drive and Overland Drive. Street, storm sewer, sidewalk, and waterline improvements will also be completed.
Project Status.
· All right-of-way has been dedicated. |
· Plans and specifications are ready to bid. Bid date will be set for November 6, 2007. |
· Stoneridge South was bid September 11, 2007, and the contractor is just beginning. |
· Signalization of Stoneridge and 6th Street is included in this project. One-half of the cost of the signal will be included in the Stoneridge South benefit district costs. |
Utility work and grading for these projects could begin this winter with paving next spring/summer. Some coordination with the water tower construction will be necessary.
Project Funding. Both of these projects are being funded through a benefit district. Overland Drive is 100% benefit district with no city participation. Stoneridge Drive includes a maximum city participation of $60,000 for additional width at the intersection of 6th Street. In addition, the city is a property owner in the benefit district (water tower) with an estimated cost of approximately $440,000, and the city is the owner of Oregon Trail Park with an estimated cost of $66,000.
Action Request. Open public hearing and pending comments:
1. Approve Ordinance 8138 levying the maximum assessments for the construction of Stoneridge Drive, Overland Drive to 6th Street, Project No. 25-CP8-806(BD). |
2. Approve Ordinance 8137 levying the maximum assessments for the construction of Overland Drive from Queens Road to Stoneridge Drive. |
Respectfully submitted,
Charles F. Soules, P.E.
Director of Public Works
CFS/je