CITY OF LAWRENCE, KANSAS |
|
|
|
|
|
|
|
PUBLIC WORKS
DEPARTMENT |
|
|
CONSTRUCTION
CONTRACT CHANGE ORDER |
|
|
|
|
|
Project Number and Name |
09-SR4-307 (C ) |
|
|
|
|
2007 Mill & Overlay
Program, Phase 1 |
|
|
|
|
|
Change Order No |
1 |
|
Date |
10/17/2007 |
|
|
|
|
|
Contractor Name & Address |
Kansas Heavy Construction |
|
|
|
19425 State Ave. |
|
|
|
|
Tonganoxie, KS 66086 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
The
following changes are being made to the referenced construction contract:that
are not included in |
|
the
original unit price bid items: |
|
|
|
|
|
|
|
|
|
|
Item No. |
Description |
|
Units |
Unit
Cost |
Quantity (+/-) |
Net
Change in Contract Price ($) |
|
|
Reduce unit
price for curb & gutter to eliminate joint sealant |
|
LF |
-$0.15 |
13107.00 |
-$1,966.05 |
|
|
Asphalt Price
Index adjustment for June and July |
|
Tons |
$0.50 |
3698.99 |
$1,849.50 |
|
|
Asphalt Price
Index adjustment for August and September |
|
Tons |
$1.50 |
3515.70 |
$5,273.55 |
|
|
Flowable Fill |
|
CY |
$95.00 |
10.00 |
$950.00 |
|
|
Subtotal |
|
|
|
|
$6,107.00 |
|
|
|
Changes
to original unit price bid items are as follows: |
|
|
|
|
|
Item No. |
Description |
|
Units |
Unit Cost |
Quantity (+/-) |
Net Change in
Contract Price ($) |
|
|
1 |
Milling - underrun |
|
SY |
$1.50 |
-2218.00 |
-$3,327.00 |
|
2 |
Asphalt Overlay
Surface - overrun |
|
Tons |
$43.75 |
64.11 |
$2,804.81 |
|
3 |
Asphalt Leveling
Course - overrun |
|
Tons |
$43.75 |
88.47 |
$3,870.56 |
|
4 |
Asphalt Full-Depth
Patch - overrun |
|
Tons |
$95.00 |
49.11 |
$4,665.45 |
|
5 |
Concrete
Full-Depth Patch - overrun |
SY |
$83.90 |
587.80 |
$49,316.42 |
|
6 |
6" Concrete
Pavement- overrun |
|
SY |
$52.80 |
157.50 |
$8,316.00 |
|
7 |
8" Concrete
Pavement - overrun |
|
SY |
$65.40 |
170.00 |
$11,118.00 |
|
8 |
24" Conc Curb
& Gutter - overrun |
|
LF |
$17.85 |
200.00 |
$3,570.00 |
|
12 |
Driveway Wedges-
underrun |
|
SY |
$8.50 |
-621.74 |
-$5,284.79 |
|
13a |
Crackfilling up to
1" - overrun |
|
LF |
$0.65 |
3357.00 |
$2,182.05 |
|
13b |
Crackfilling >
1" - underrun |
|
LF |
$1.00 |
-3067.00 |
-$3,067.00 |
|
18 |
Asphalt Test Cores -
underrun |
|
EA |
$60.00 |
-9.00 |
-$540.00 |
|
19 |
TemporarySurfacing -
overrun |
|
Tons |
$15.50 |
52.00 |
$806.00 |
|
21 |
Traffic Control -
underrun |
|
EA |
$1.00 |
-11569.50 |
-$11,569.50 |
|
|
Subtotal |
|
|
|
|
$62,861.01 |
|
|
|
|
|
|
|
|
|
|
Original Contract Amount |
|
$864,900.00 |
|
|
Net Change by Previous
Change Order(s) |
|
$0.00 |
|
|
Net Change by This Change
Order |
|
$68,968.00 |
|
|
New Contract Amount |
|
$933,868.00 |
|
|
|
|
Original Contract Time or
Completion Date |
|
60 working days |
|
|
Net Change by Previous
Change Order(s) |
|
N/A |
|
|
Net Change by This Change
Order |
|
N/A |
|
|
New Contract Time or
Completion Date |
|
N/A |
|
|
|
|
|
|
Approved By: |
|
|
|
|
|
|
|
Date: |
|
|
|
Contractor |
|
|
|
|
|
|
Date: |
|
|
|
Asst Dir of Public Works |
|
|
|
|
|
|
|
|
|
|
|