| Project Number and Name | 09-SR4-307 (C ) | ||||||||
| 2007 Mill & Overlay Program, Phase 1 | |||||||||
| Change Order No | 1 | Date | 10/17/2007 | ||||||
| Contractor Name & Address | Kansas Heavy Construction | ||||||||
| 19425 State Ave. | |||||||||
| Tonganoxie, KS 66086 | |||||||||
| The following changes are being made to the referenced construction contract:that are not included in | |||||||||
| the original unit price bid items: | |||||||||
| Item No. | Description | Units | Unit Cost | Quantity (+/-) | Net Change in Contract Price ($) | ||||
| Reduce unit price for curb & gutter to eliminate joint sealant | LF | -$0.15 | 13107.00 | -$1,966.05 | |||||
| Asphalt Price Index adjustment for June and July | Tons | $0.50 | 3698.99 | $1,849.50 | |||||
| Asphalt Price Index adjustment for August and September | Tons | $1.50 | 3515.70 | $5,273.55 | |||||
| Flowable Fill | CY | $95.00 | 10.00 | $950.00 | |||||
| Subtotal | $6,107.00 | ||||||||
| Changes to original unit price bid items are as follows: | |||||||||
| Item No. | Description | Units | Unit Cost | Quantity (+/-) | Net Change in Contract Price ($) | ||||
| 1 | Milling - underrun | SY | $1.50 | -2218.00 | -$3,327.00 | ||||
| 2 | Asphalt Overlay Surface - overrun | Tons | $43.75 | 64.11 | $2,804.81 | ||||
| 3 | Asphalt Leveling Course - overrun | Tons | $43.75 | 88.47 | $3,870.56 | ||||
| 4 | Asphalt Full-Depth Patch - overrun | Tons | $95.00 | 49.11 | $4,665.45 | ||||
| 5 | Concrete Full-Depth Patch - overrun | SY | $83.90 | 587.80 | $49,316.42 | ||||
| 6 | 6" Concrete Pavement- overrun | SY | $52.80 | 157.50 | $8,316.00 | ||||
| 7 | 8" Concrete Pavement - overrun | SY | $65.40 | 170.00 | $11,118.00 | ||||
| 8 | 24" Conc Curb & Gutter - overrun | LF | $17.85 | 200.00 | $3,570.00 | ||||
| 12 | Driveway Wedges- underrun | SY | $8.50 | -621.74 | -$5,284.79 | ||||
| 13a | Crackfilling up to 1" - overrun | LF | $0.65 | 3357.00 | $2,182.05 | ||||
| 13b | Crackfilling > 1" - underrun | LF | $1.00 | -3067.00 | -$3,067.00 | ||||
| 18 | Asphalt Test Cores - underrun | EA | $60.00 | -9.00 | -$540.00 | ||||
| 19 | TemporarySurfacing - overrun | Tons | $15.50 | 52.00 | $806.00 | ||||
| 21 | Traffic Control - underrun | EA | $1.00 | -11569.50 | -$11,569.50 | ||||
| Subtotal | $62,861.01 | ||||||||
| Original Contract Amount | $864,900.00 | ||||||||
| Net Change by Previous Change Order(s) | $0.00 | ||||||||
| Net Change by This Change Order | $68,968.00 | ||||||||
| New Contract Amount | $933,868.00 | ||||||||
| Original Contract Time or Completion Date | 60 working days | ||||||||
| Net Change by Previous Change Order(s) | N/A | ||||||||
| Net Change by This Change Order | N/A | ||||||||
| New Contract Time or Completion Date | N/A | ||||||||