Memorandum
City of Lawrence
Department of Public Works
TO: |
David L. Corliss, Cynthia Boecker |
FROM: |
Chuck Soules |
CC: |
Shoeb Uddin, Matt Bond, Dena Mezger, David Woosley |
Date: |
October 17, 2007 |
RE: |
19th Street (Ohio Street to Alabama Street), Geometric Improvements Update - Project No. 61-GI2-1104(C) |
Project Details
This project includes geometric improvements on 19th Street between Ohio Street and Alabama Street (see attached map). More specifically, the improvements will include widening of existing pavement width to add and lengthen center/left turn lanes on 19th Street, installation of a bus turn-out for school buses on Louisiana Street, mill and overlay, construction of a sidewalk on the north side of 19th Street, reconstruction of sidewalk on the south side of 19th Street, construction of storm water inlets, and traffic signal improvements at the intersection of 19th and Louisiana. This project also includes replacement and relocation of an old 1930’s water main, the entire cost of which will be paid by the Utilities Department.
Project History / Status
November 23, 2004: |
City Commission passed Resolution 6571 authorizing the issuance of General Obligation Bonds for a principal maximum amount of $250,000.00. |
January 18, 2005: |
City Commission approved a contract with BG Consultants in the amount of $37,180.08 to perform a Feasibility Study and Report. |
April 2006: |
City Commission added this project to the 5-year Plan with KDOT. |
May 16, 2005 |
Public meeting to gather input. |
November 14, 2005 |
Met with School Board. |
March 10, 2005 |
Stakeholder meeting – included Lawrence High School, Cordley School, Centennial Elementary School, Old West Lawrence Neighborhood Association, and University Place. |
October 19, 2005 |
School Site Council Meeting. |
January 23, 2006 |
Met with School Board. |
February 1, 2006 |
Met with Site Councils. |
February 22, 2006 |
Public meeting for comment on study. |
July 11, 2006 |
City Commission provided direction for improvements. |
October 16, 2007 |
Public open house. |
The project schedule is very aggressive with plans to be completed by December 2007 and construction to be completed by August, 2008. 19th Street is scheduled for mill and overlay as part of the 2008 Pavement Management Program. Combining these two projects will provide a complete/finished project for the entire length of 19th Street and will ensure efficient use of scarce funds.
Project Funding
Following are approximate costs of the project:
State maximum participation |
$294,000 |
School District agreed to pay for the bus turnout lane |
$90,000 |
Feasibility Study and Report |
$37,000 |
Engineering (BG Consultants) |
$78,000 |
Estimated street construction |
$800,000 |
Waterline (Office Check Estimate) |
$288,000 |
Total |
$1,587,000 |
Total does not include right-of-way costs. Project costs were anticipated and included in the CIP.
Traffic Control/Schedule
The project is expected to bid in February 2008. The water main lies behind the curb and gutter and could be completed in April/May with minor traffic impacts on 19th Street. The street work cannot begin until schools are out and, therefore, we are specifying that 19th Street from Ohio to Alabama be closed from June 1 – July 31. The amount of work to be completed in this two month window is rather extensive and the contractor will need every bit of this time to complete the project. Discussion with neighbors and property owners received no objections to closing the road.
We will place dated road construction signs beginning a week prior to closing the road. Detours using Massachusetts, 23rd Street, 15th Street, and Naismith Drive will be established.
Please let me know if additional information is needed.
Respectfully submitted,
Charles F. Soules, P.E.
Director of Public Works
CFS/je