ITEM DESCRIPTION UNIT QUANTITY UNIT PRICE AMOUNT UNIT PRICE AMOUNT UNIT PRICE AMOUNT UNIT PRICE AMOUNT UNIT PRICE AMOUNT
1 Clearing and Grubbing L.S. 1  $       6,121.79  $           6,121.79  $       7,500.00  $          7,500.00  $   5,350.00  $       5,350.00  $    7,050.00  $      7,050.00  $    9,975.00  $           9,975.00
2 Removal of Existing Structures L.S. 1  $       7,100.00  $           7,100.00  $       2,500.00  $          2,500.00  $   6,450.00  $       6,450.00  $  12,325.00  $    12,325.00  $  13,920.00  $         13,920.00
3 Unclassified Excavation C.Y. 2,362  $               7.30  $         17,242.60  $               4.00  $          9,448.00  $           7.00  $    16,534.00  $          14.80  $    34,957.60  $          26.50  $         62,593.00
4 Compaction (90%) C.Y. 1,222  $               1.50  $           1,833.00  $               1.50  $          1,833.00  $           1.60  $       1,955.20  $            1.00  $      1,222.00  $            1.50  $           1,833.00
5 Compaction (95%) C.Y. 975  $               1.50  $           1,462.50  $               1.50  $          1,462.50  $           1.60  $       1,560.00  $            2.00  $      1,950.00  $            2.00  $           1,950.00
6 9" Fly Ash Stabilization S.Y. 3,899  $               3.60  $         14,036.40  $               4.00  $        15,596.00  $           3.70  $    14,426.30  $            5.79  $    22,575.21  $            4.73  $         18,442.27
7 Asphalt Surfacing (Surface Course) (BM-2) TON 342  $            49.00  $         16,758.00  $             51.70  $        17,681.40  $         49.90  $    17,065.80  $          53.89  $    18,430.38  $          52.40  $         17,920.80
8 Asphalt Surfacing (Base Course) (BM-2B)  TON 1,556  $            45.50  $         70,798.00  $             48.05  $        74,765.80  $         43.90  $    68,308.40  $          47.41  $    73,769.96  $          46.09  $         71,716.04
9 6" Concrete Entrance Pavement (Reinforced) (A.E.) S.Y. 160.2  $            39.90  $           6,391.98  $             39.32  $          6,299.06  $         42.00  $       6,728.40  $          47.02  $      7,532.60  $          61.00  $           9,772.20
10 6" Stamped, Colored Concrete (Reinforced) (A.E.) S.Y. 123  $            48.50  $           5,965.50  $             70.00  $          8,610.00  $         56.00  $       6,888.00  $          94.82  $    11,662.86  $       136.50  $         16,789.50
11 Concrete Curb and Gutter (A.E.) L.F. 2,224.8  $               8.95  $         19,911.96  $             12.18  $        27,098.06  $         13.00  $    28,922.40  $          14.71  $    32,726.81  $          13.00  $         28,922.40
12 4" Concrete Sidewalk (A.E.) S.Y. 435.2  $            21.90  $           9,530.88  $             27.30  $        11,880.96  $         26.00  $    11,315.20  $          32.81  $    14,278.91  $          32.50  $         14,144.00
13 6" Concrete Sidewalk (Fiber Reinforced) (A.E.) S.Y. 964.9  $            36.35  $         35,074.12  $             33.60  $        32,420.64  $         36.00  $    34,736.40  $          38.28  $    36,936.37  $          36.00  $         34,736.40
14 6' Access Ramp EACH 1  $          945.00  $              945.00  $       1,155.00  $          1,155.00  $      460.00  $          460.00  $    1,262.00  $      1,262.00  $    2,250.00  $           2,250.00
15 10' Access Ramp EACH 3  $       1,809.00  $           5,427.00  $       1,496.25  $          4,488.75  $      875.00  $       2,625.00  $    2,054.00  $      6,162.00  $    1,900.00  $           5,700.00
16 10' Access Ramp without detectable warnings EACH 2  $       1,500.00  $           3,000.00  $       1,155.00  $          2,310.00  $      350.00  $          700.00  $    1,296.00  $      2,592.00  $       850.00  $           1,700.00
17 Woven Wire Type B Fence L.F. 304  $            31.50  $           9,576.00  $             10.00  $          3,040.00  $         20.00  $       6,080.00  $          20.13  $      6,119.52  $          18.38  $           5,587.52
18 Concrete Manhole Collar EACH 1  $          430.00  $              430.00  $           250.00  $             250.00  $      900.00  $          900.00  $       651.00  $          651.00  $    1,500.00  $           1,500.00
19 5' x 4' Standard Curb Inlet EACH 1  $       2,720.00  $           2,720.00  $       2,442.00  $          2,442.00  $   2,950.00  $       2,950.00  $    3,490.00  $      3,490.00  $    3,500.00  $           3,500.00
20 15" Storm Sewer (RCP) (In Place) L.F. 14  $            93.70  $           1,311.80  $             45.00  $             630.00  $         86.00  $       1,204.00  $       111.50  $      1,561.00  $       135.00  $           1,890.00
21 12" Storm Sewer (CMP) (In Place) L.F. 28  $            36.70  $           1,027.60  $             20.00  $             560.00  $         38.00  $       1,064.00  $          79.00  $      2,212.00  $          46.00  $           1,288.00
22 12" End Section (CM) EACH 2  $          250.00  $              500.00  $           112.35  $             224.70  $      350.00  $          700.00  $       580.00  $      1,160.00  $       175.00  $              350.00
23 Connect to Existing Storm Sewer EACH 1  $          470.00  $              470.00  $           500.00  $             500.00  $      150.00  $          150.00  $    1,480.00  $      1,480.00  $       828.00  $              828.00
24 12" D.I. Waterline (In Place) L.F. 616  $            38.00  $         23,408.00  $             44.10  $        27,165.60  $         43.00  $    26,488.00  $          76.68  $    47,234.88  $          71.00  $         43,736.00
25 12" M.J. Gate Valve EACH 4  $       1,600.00  $           6,400.00  $       1,401.75  $          5,607.00  $   1,350.00  $       5,400.00  $    1,814.40  $      7,257.60  $    1,575.00  $           6,300.00
26 8" M.J. Gate Valve EACH 1  $          980.00  $              980.00  $           756.00  $             756.00  $      750.00  $          750.00  $       972.00  $          972.00  $       850.00  $              850.00
27 Standard Fire Hydrant Setting EACH 2  $       2,375.00  $           4,750.00  $       2,089.00  $          4,178.00  $   2,000.00  $       4,000.00  $    3,834.00  $      7,668.00  $    3,325.00  $           6,650.00
28 Connect to Existing Waterline EACH 2  $          368.00  $              736.00  $           637.35  $          1,274.70  $      625.00  $       1,250.00  $       702.00  $      1,404.00  $       600.00  $           1,200.00
29 Remove and Reset Sign EACH 1  $          185.00  $              185.00  $           194.25  $             194.25  $      190.00  $          190.00  $       231.25  $          231.25  $       194.25  $              194.25
30 Permanent Sign EACH 3  $          237.50  $              712.50  $           249.38  $             748.14  $      250.00  $          750.00  $       296.88  $          890.64  $       249.38  $              748.14
31 Pavement Marking (White) (6") L.F. 324  $               1.65  $              534.60  $               1.73  $             560.52  $           1.70  $          550.80  $            2.07  $          670.68  $            1.73  $              560.52
32 Pavement Marking (White) (24") L.F. 174  $            14.00  $           2,436.00  $             14.70  $          2,557.80  $         14.00  $       2,436.00  $          17.50  $      3,045.00  $          14.70  $           2,557.80
33 Pavement Marking (Yellow) (4") L.F. 666  $               1.25  $              832.50  $               1.31  $             872.46  $           1.50  $          999.00  $            1.57  $      1,045.62  $            1.31  $              872.46
34 Pavement Marking Sysbol (White) (LT Arrow) EACH 4  $          175.00  $              700.00  $           183.75  $             735.00  $      180.00  $          720.00  $       218.75  $          875.00  $       183.75  $              735.00
35 Pavement Marking Symbol (White) (Lane-Reduction Arrow) EACH 2  $          250.00  $              500.00  $           262.50  $             525.00  $      250.00  $          500.00  $       312.50  $          625.00  $       262.50  $              525.00
36 Silt Fence L.F. 1,486  $               1.90  $           2,823.40  $               1.35  $          2,006.10  $           1.75  $       2,600.50  $            2.50  $      3,715.00  $            2.00  $           2,972.00
37 Temporary Construction Entrance EACH 1  $       1,050.00  $           1,050.00  $           500.00  $             500.00  $   1,250.00  $       1,250.00  $    2,500.00  $      2,500.00  $    2,000.00  $           2,000.00
38 Temporary Seeding L.S. 1  $       1,633.00  $           1,633.00  $       1,260.00  $          1,260.00  $      750.00  $          750.00  $    3,360.00  $      3,360.00  $    2,940.00  $           2,940.00
39 Traffic Control L.S. 1  $       2,700.00  $           2,700.00  $       2,835.00  $          2,835.00  $   3,900.00  $       3,900.00  $    3,375.00  $      3,375.00  $    2,835.00  $           2,835.00
40 Construction Staking  L.S. 1  $       3,230.00  $           3,230.00  $       3,150.00  $          3,150.00  $   3,100.00  $       3,100.00  $    3,800.00  $      3,800.00  $    3,255.00  $           3,255.00
41 Seeding, Fertilizing and Mulching L.S. 1  $       2,650.00  $           2,650.00  $       1,620.00  $          1,620.00  $   2,000.00  $       2,000.00  $    5,400.00  $      5,400.00  $    4,725.00  $           4,725.00
42 Mobilization L.S. 1  $       2,500.00  $           2,500.00  $       7,500.00  $          7,500.00  $   5,185.00  $       5,185.00  $  20,990.00  $    20,990.00  $  18,099.00  $         18,099.00
  GRAND TOTAL    $      296,395.13    $     296,741.44    $  299,892.40    $  417,166.89    $       429,063.30