CITY OF LAWRENCE, KANSAS
PUBLIC WORKS DEPARTMENT
CONSTRUCTION CONTRACT CHANGE ORDER
Project Number and Name  08-SR3-307(C )    
2007 Microsurfacing Program
Change Order No 1 (Final) Date 9/11/2007
Contractor Name & Address Vance Brothers, Inc  
5201 Brighton    
Kansas city MO 64130  
       
The following changes are being made to the referenced construction contract:that are not included in 
the original unit price bid items:
             
Item No. Description   Units Unit Cost Quantity  (+/-) Net Change in Contract Price ($)
  Asphalt Patch - Skin Patch   Tons $217.93 539.0 $117,464.27
  Subtotal         $117,464.27
Changes to original unit price bid items are as follows:
Item No. Description   Units Unit Cost Quantity  (+/-) Net Change in Contract Price ($)
1 Microsurfacing   SY $1.76 -1273.0 -$2,240.48
3 Asphalt Patch - Full Depth   Tons $101.00 -705.0 -$71,205.00
4 Traffic Control       Force Acct $22,468.55
  Subtotal         -$50,976.93
Original Contract Amount See Note $468,316.50
Net Change by Previous Change Order(s) $0.00
Net Change by This Change Order $66,487.34
New Contract Amount $534,803.84
Original Contract Time or Completion Date 45 working days
Net Change by Previous Change Order(s) 0
Net Change by This Change Order 0
New Contract Time or Completion Date N/A
Note: An additional $56,683.50 was added at the time of award to cover additional work anticipated
to be required for a total approved amount of $525,000. The actual increase over the approved 
amount is $9,803.84.
Approved By:
    Date:  
Contractor
    Date:  
Asst Dir of Public Works