CITY OF LAWRENCE, KANSAS |
|
|
|
|
|
|
|
PUBLIC WORKS DEPARTMENT |
|
|
CONSTRUCTION CONTRACT CHANGE ORDER |
|
|
|
|
|
Project Number and Name |
08-SR3-307(C ) |
|
|
|
|
|
2007 Microsurfacing
Program |
|
|
|
|
|
Change Order No |
1 (Final) |
|
Date |
9/11/2007 |
|
|
|
|
|
Contractor Name & Address |
Vance Brothers, Inc |
|
|
|
|
5201 Brighton |
|
|
|
|
|
Kansas city MO 64130 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
The
following changes are being made to the referenced construction contract:that
are not included in |
|
the
original unit price bid items: |
|
|
|
|
|
|
|
|
|
|
Item No. |
Description |
|
Units |
Unit
Cost |
Quantity (+/-) |
Net
Change in Contract Price ($) |
|
|
Asphalt Patch - Skin Patch |
|
Tons |
$217.93 |
539.0 |
$117,464.27 |
|
|
Subtotal |
|
|
|
|
$117,464.27 |
|
|
|
Changes
to original unit price bid items are as follows: |
|
|
|
|
|
Item No. |
Description |
|
Units |
Unit Cost |
Quantity (+/-) |
Net Change in
Contract Price ($) |
|
|
1 |
Microsurfacing |
|
SY |
$1.76 |
-1273.0 |
-$2,240.48 |
|
|
3 |
Asphalt Patch - Full
Depth |
|
Tons |
$101.00 |
-705.0 |
-$71,205.00 |
|
|
4 |
Traffic Control |
|
|
|
Force Acct |
$22,468.55 |
|
|
Subtotal |
|
|
|
|
-$50,976.93 |
|
|
|
|
|
|
Original Contract Amount |
|
See Note |
$468,316.50 |
|
|
Net Change by Previous
Change Order(s) |
|
$0.00 |
|
|
Net Change by This Change
Order |
|
$66,487.34 |
|
|
New Contract Amount |
|
$534,803.84 |
|
|
|
|
Original Contract Time or
Completion Date |
|
45 working days |
|
|
Net Change by Previous
Change Order(s) |
|
0 |
|
|
Net Change by This Change
Order |
|
0 |
|
|
New Contract Time or
Completion Date |
|
N/A |
|
|
|
|
|
|
Note: An additional
$56,683.50 was added at the time of award to cover additional work
anticipated |
|
|
to
be required for a total approved amount of $525,000. The actual increase over
the approved |
|
|
amount is $9,803.84. |
|
|
|
|
Approved By: |
|
|
|
|
|
|
|
Date: |
|
|
|
Contractor |
|
|
|
|
|
|
Date: |
|
|
|
Asst Dir of Public Works |
|
|
|
|
|
|
|
|
|
|
|