ESTIMATE
ITEM   UNIT QUANTITY UNIT PRICE  AMOUNT 
 
Demolition
1 Track Removal for entire corridor FREE 1 $0.00  $              -  
2 Tie Removal for entire corridor FREE 1 $0.00  $              -  
3 Dumpster Rental and Moblization for removed ties L.S. 1 $1,500.00  $    1,500.00
4 Demolition for entire (main) trail MILE 1.46 $2,500.00  $    3,650.00
5 Eradicating of Oregon St. (road to be vacated) L.S. 1 $5,000.00  $    5,000.00
6 Ward St. Connection Demolition L.S. 1 $600.00  $       600.00
7 Parnell Park Connection Demolition L.S. 1 $1,000.00  $    1,000.00
    SUBTOTAL:  $    8,650.00
 
Mobilization
8 Mobilization for Phase I L.S. 1 $7,500  $    7,500.00
    SUBTOTAL:  $    7,500.00
 
Construction Engineering Design and Bidding
9 Construction Engineering Design and Bidding for Phase I L.S. 1 $40,000  $   40,000.00
    SUBTOTAL:  $   40,000.00
 
Construction Staking
10 Construction Staking for Phase I L.S. 1 $10,000  $   10,000.00
    SUBTOTAL:  $   10,000.00
 
Clearing & Grubbing
11 Along Main Trail MILE 1.46 $2,500  $    3,650.00
    SUBTOTAL:  $    3,650.00
 
Grading & Compaction
12 Main Trail L.S. 1 $5,500  $    5,500.00
    SUBTOTAL:  $    5,500.00
 
Concrete Walkways
13 Hobbs Park to beginning of Trail (10' Wide) S.F. 5,170 $4.50 $23,265.00
14 11th to Ward St. Connection (Main Trail) (10' Wide) S.F. 539,210 $4.50 $2,426,445.00
15 Hanscom-Tappan Connection (5' Wide) S.F. 465 $4.50 $2,092.50
16 Ward St. Connection (10' Wide) S.F. 930 $4.50 $4,185.00
    SUBTOTAL: $2,455,987.50
           
Concrete Retaining Wall
17 Retaining Wall Along 11th St. Connection L.S. 1 $30,000.00 $30,000.00
    SUBTOTAL: $30,000.00
 
Access Control
18 Collapsable Bollards E.A. 8 $600 $4,800.00
19 Boulders (including delivery) L.S. 1 $10,000 $10,000.00
    SUBTOTAL: $14,800.00
 
Amenities
20 Trash Receptacles  E.A. 12 $250 $3,000.00
21 Benches E.A. 15 $350 $5,250.00
    SUBTOTAL: $8,250.00
 
Seeding
22 Main Trail  L.S. 1 $1,500 $1,500.00
23 Ward St. Connection L.S. 1 $300 $300.00
24 Hanscom-Tappan Connection L.S. 1 $500 $500.00
    SUBTOTAL: $2,300.00
 
Erosion Control
25 Main Trail  L.S. 1 $6,000  $    6,000.00
    SUBTOTAL:  $    6,000.00
 
Pipe Placement
26 Random Storm Drainage Pipe Placement  L.S. 1 $5,000  $    5,000.00
    SUBTOTAL:  $    5,000.00
           
Bridges
27 Pre-fab 30 foot Pedestrian Bridge (Parnell Park) L.S. 1 $55,000  $   55,000.00
    SUBTOTAL:  $   55,000.00
 
 
Property Acquisition of Remaining Trail
28 Esm't Through DaVol L.S. 1    $              -  
29 Corner of Johnson Connection L.S. 1    $              -  
    SUBTOTAL:  $              -  
 
SUBTOTAL FOR PHASE ONE: $2,652,637.5
       
15% CONTINGENCY:  $ 397,895.63
TOTAL FOR PHASE ONE: $3,050,533.1