Memorandum

City of Lawrence

Public Works

TO:

Dave Corliss, Debbie Van Saun

FROM:

Chuck Soules

Date:

April 18, 2007

RE:

31st Street – Haskell Avenue to O’Connell Road

KDOT Project No. 23 U-2117-01 – City Project No. 18-CP7-507(S)

CONSENT AGENDA ITEM

 

 

 

 

 

 

 

 

Please place the following item on the City Commission consent agenda for consideration at its August 23, 2007 meeting:

 

Project DetailsIn 2006 the City was informed of an $800,000 earmark for the construction of 31st Street from Haskell Avenue to O’Connell Road.  The earmark does not have any conditions attached; essentially this means the funds can be used for preliminary engineering (design), right-of-way acquisition, and construction.  The project will be administered by KDOT.  KDOT can “charge” a 1% administration cost, leaving the total amount available at $792,000.

 

The City submitted a Request for Construction Project on June 15, 2006 to initiate the project.  The project does have a schedule with a tentative letting of October 2008; however, we have to have the project complete in ten years so the letting date could be moved.

 

Project Status KDOT will require “Field Check Plans” which need to be 60-70% complete prior to purchasing right-of-way. 

 

Work items include:

·        Execute City-State Agreement - complete

·        Begin consultant selection process – City Commission approved April 24, 2007.

·        Consultant selection:  The City received nine proposals from engineering firms for this project.  Four firms were interviewed: TranSystems, Professional Engineering Consultants, Wilson & Co., and Affinis.  The interview panel included: Brad Finkleldei from the MPO; Michael Caron from “Save the Wakarusa Wetlands”; Keith Browning, Douglas County Engineer; Shoeb Uddin, City Engineer; and Chuck Soules, Director of Public Works.  Firms were evaluated based on their project understanding and approach, work elements and sequencing, experience and qualifications, public participation, and environmental awareness.

·        Meet with City Manager and City Commission to discuss 31st Street Study and goals for project

·        Public process

·        “Field Check Plan”  completion

·        Property acquisition

 

Pending funding:

·         Proceed to final plan

·          Bid/construct

 

 

 

 

 

 

Action Request

1. Request approval from City Commission to enter into negotiation with Wilson & Co for professional services for 31st Street, Haskell Avenue to O’Connell Road.

2.  Establish date to discuss Commission goals for this project so we might begin establishing Scope of Services.

 