| CITY OF LAWRENCE, KANSAS | |||||||||
| PUBLIC WORKS DEPARTMENT | |||||||||
| CONSTRUCTION CONTRACT CHANGE ORDER | |||||||||
| Project Number and Name | 1-SR1-107 S) | ||||||||
| KLINK Resurfacing - Iowa St | |||||||||
| Change Order No | 1 | Date | 1-Aug-07 | ||||||
| Contractor Name & Address | LRM Industries | ||||||||
| 1404 E. 24th St, Suite A | |||||||||
| Lawrence, KS 66046 | |||||||||
| The following changes are being made to the referenced construction contract:that are not included in | |||||||||
| the original unit price bid items: | |||||||||
| Item No. | Description | Units | Unit Cost | Quantity (+/-) | Net Change in Contract Price ($) | ||||
| 1 | Milling S. Iowa frontage road | SY | $1.80 | 1,476 | $2,656.80 | ||||
| 2 | Asphalt overlay leveling course | Tons | $51.60 | 109 | $5,624.40 | ||||
| SUBTOTAL | $8,281.20 | ||||||||
| Changes to original unit price bid items are as follows: | N/A | ||||||||
| Item No. | Description | Units | Unit Cost | Quantity (+/-) | Net Change in Contract Price ($) | ||||
| Original Contract Amount | $478,963.74 | ||||||||
| Net Change by Previous Change Order(s) | $0.00 | ||||||||
| Net Change by This Change Order | $8,281.20 | ||||||||
| New Contract Amount | $487,244.94 | ||||||||
| Original Contract Time or Completion Date | 30 working days | ||||||||
| Net Change by Previous Change Order(s) | N/A | ||||||||
| Net Change by This Change Order | N/A | ||||||||
| New Contract Time or Completion Date | N/A | ||||||||
| Approved By: | |||||||||
| Date: | |||||||||
| Contractor | |||||||||
| Date: | |||||||||
| Asst Dir of Public Works | |||||||||