CITY OF LAWRENCE, KANSAS |
|
|
|
|
|
|
|
PUBLIC WORKS DEPARTMENT |
|
|
CONSTRUCTION CONTRACT CHANGE ORDER |
|
|
|
|
|
Project Number and Name |
15-CP4-404C |
|
|
|
|
|
Kasold- 22nd to Bob
Billings Pkwy |
|
|
|
|
|
Change Order No |
2 |
(FINAL) |
Date |
July 26,2007 |
|
|
|
|
|
Contractor Name & Address |
RD Johnson Excavating
Company |
|
|
|
1705 N 1399 Road |
|
|
|
|
Lawrence, KS 66046 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
The
following additions and/or deletions are being made to the referenced
construction contract: |
|
|
|
|
Description |
|
Units |
Unit Cost |
Quantity (+/-) |
Net Change in
Contract Price ($) |
|
1 |
Add
18" CMP to keep storm water from overtopping curb |
|
LS |
$1,500.75 |
1 |
$1,500.75 |
|
2 |
Add
lattice-top wooden fence to match resident's existing fence |
|
LF |
$47.15 |
100 |
$4,715.00 |
|
3 |
Add
retaining wall for drainage channel |
|
LS |
$1,649.80 |
1 |
$1,649.80 |
|
4 |
Upgrade
coarse aggregate in sidewalk to granite |
|
LS |
$1,052.45 |
1 |
$1,052.45 |
|
5 |
Add
safety partition to ends of retaining wall |
|
LS |
$2,295.40 |
1 |
$2,295.40 |
|
6 |
Replace
seeding with buffalo grass sod at 2106 Kasold |
|
LS |
$5,234.50 |
1 |
$5,234.50 |
|
7 |
Remove
and replace cracked curb & gutter |
|
LF |
$24.38 |
114 |
$2,779.40 |
|
8 |
Remove
and replace island at 22nd Terr for traffic access |
|
LS |
$6,410.06 |
1 |
$6,410.06 |
|
9 |
Upgrade
pavement marking materials |
|
LS |
$63,972.00 |
1 |
$63,972.00 |
|
10 |
Additional
concrete work including sidewalk, curb replacement, and misc paving to
improve existing walks, drainage & side slopes |
|
LS |
$40,260.30 |
1 |
$40,260.30 |
|
11 |
Additional landscaping at 2104
Kasold |
|
LS |
$414.00 |
1 |
$414.00 |
|
12 |
Mill,
patch, overlay, replace signal loop & install pavement marking between
22nd Terr and Clinton Parkway |
|
LS |
$73,978.07 |
1 |
$73,978.07 |
|
13 |
Unused
balance for temporary traffic control (CO No. 1) |
|
LS |
$1,634.00 |
-1 |
-$1,634.00 |
|
14 |
Delete
overtime for waterline work (CO No. 1) |
|
LS |
$1,311.00 |
-1 |
-$1,311.00 |
|
15 |
Unused
balance for wrought iron fence (CO No. 1) |
|
LS |
$7,944.25 |
-1 |
-$7,944.25 |
|
16 |
Unused
balance for rock wall at 2022 Kasold (CO No 1) |
|
Ls |
$2,650.00 |
-1 |
-$2,650.00 |
|
17 |
Delete
driveway pavement at 3501 Scioto & 1840 Kasold (CO No. 1) - included in
item 34 below |
|
SF |
$4.10 |
-832.89 |
-$3,414.85 |
|
18 |
Delete
concrete testing (CO No 1) - paid directly to testing lab |
|
SET |
$100.00 |
-30 |
-$3,000.00 |
|
19 |
Delete
sprinkler repairs (CO No 1) paid directly to property owner |
|
LS |
$906.15 |
-1 |
-$906.15 |
|
20 |
Delete
mailbox (CO No 1) |
|
LS |
$13.99 |
-1 |
-$13.99 |
|
21 |
Unused
balance sprinkler repairs (CO No. 1) |
|
EA |
$2,150.00 |
-4 |
-$8,600.00 |
|
22 |
Additional
costs for Signal Controller Box replacement |
|
LS |
$2,470.00 |
1 |
$2,470.00 |
|
23 |
Trenching
for streetlight installation |
|
LF |
$3.50 |
1757 |
$6,150.00 |
|
|
SUBTOTAL |
|
|
|
|
$183,407.49 |
|
|
|
Changes
to bid items are as follows: |
|
|
|
|
|
Item No. |
Description |
|
Units |
Unit Cost |
Quantity (+/-) |
Net Change in
Contract Price ($) |
|
|
|
Section 1- Street,
Storm Sewer |
|
|
|
|
|
|
|
19 |
6'
Wood Fence - Credit for overpayment |
LF |
20.6 |
-226 |
-$4,655.60 |
|
|
31 |
4"
Edge Drain - Credit for overpayment |
LF |
7.9 |
-2105 |
-$16,629.50 |
|
|
34 |
6" Concrete
Driveway |
|
SF |
$4.10 |
1298.4 |
$5,323.44 |
|
35 |
Pavement Marking
Cross Walk |
|
EA |
$260.00 |
-16 |
-$4,160.00 |
|
36 |
Pavement Marking Left
Turn Arrow |
|
EA |
$180.00 |
-16 |
-$2,880.00 |
|
37 |
Pavement
Marking Right Turn Arrow |
EA |
$180.00 |
-12 |
-$2,160.00 |
|
38 |
4" Broken Yellow
Line |
|
LF |
$1.30 |
-130 |
-$169.00 |
|
39 |
6" Broken White
Line |
|
LF |
$2.60 |
-2200 |
-$5,720.00 |
|
40 |
6" Dotted White
Line |
|
LF |
$2.60 |
-92 |
-$239.20 |
|
41 |
6" Solid White
Line |
|
LF |
$2.60 |
-1593 |
-$4,141.80 |
|
42 |
4" Double Yellow
Line |
|
LF |
$2.60 |
-1792 |
-$4,659.20 |
|
43 |
4" Solid Yellow
Line |
|
LF |
$1.30 |
-505 |
-$656.50 |
|
44 |
12" Solid White
Line |
|
LF |
$7.20 |
-103 |
-$741.60 |
|
45 |
12" Solid Yellow
Line |
|
LF |
$7.20 |
-180 |
-$1,296.00 |
|
46 |
24" Solid White
Line (Stop Bar) |
|
LF |
$14.30 |
-53 |
-$757.90 |
|
|
50 |
Silt Fence |
|
LF |
$1.70 |
1284 |
$2,182.80 |
|
|
Section 2 - Waterline |
|
|
|
|
|
|
10 |
Service Connection |
|
EA |
$1,230.00 |
1 |
$1,230.00 |
|
11 |
Service Connection
w/Meter |
|
EA |
$1,230.00 |
1 |
$1,230.00 |
|
|
SUBTOTAL |
|
|
|
|
-$38,900.06 |
|
|
|
|
Original Contract Amount |
|
$5,483,332.90 |
|
|
Net Change by Previous
Change Order(s) |
|
$81,859.50 |
|
|
Net Change by This Change
Order |
|
$144,507.43 |
|
|
New Contract Amount |
|
$5,709,699.83 |
|
|
|
|
Original Contract Time or
Completion Date |
|
6-Oct-07 |
|
|
Net Change by Previous
Change Order(s) |
|
N/A |
|
|
Net Change by This Change
Order |
|
|
|
|
New Contract Time or
Completion Date |
|
N/A |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Approved By: |
|
|
|
|
|
|
|
Date: |
|
|
|
Contractor |
|
|
|
|
|
|
|
Date: |
|
|
|
Engineer/Project Inspector |
|
|
|
|
|
|
Date: |
|
|
|
Asst Dir of Public Works |
|
|
|
|
|
|
|
|
|
|
|