CITY OF LAWRENCE, KANSAS |
|
|
|
|
|
|
|
PUBLIC WORKS DEPARTMENT |
|
|
CONSTRUCTION CONTRACT CHANGE ORDER |
|
|
|
|
|
Project Number and Name |
02-SR2-107 © |
C |
|
|
|
|
|
2007 Crack Seal Program |
|
|
|
|
|
|
Change Order No |
1 |
|
Date |
5/25/2007 |
|
|
|
|
|
Contractor Name & Address |
Missouri Pavement
Maintenance |
|
|
|
4400 A North Cobbler |
|
|
|
|
Independence, MO 64058 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
The
following changes are being made to the referenced construction contract: |
|
|
|
Addition
of material to crack seal more streets than included in original program.
Original bid was below |
|
project
budget so funding is available without going over budgeted amount ($300,000). |
|
|
|
|
|
|
|
|
|
|
|
Changes
to bid items are as follows: |
|
|
|
|
|
Item No. |
Description |
|
Units |
Unit Cost |
Quantity (+/-) |
Net Change in
Contract Price ($) |
|
|
1 |
Crack Seal |
|
LBS. |
$1.06 |
44000 |
$46,640.00 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Original Contract Amount |
|
$239,500.00 |
|
|
Net Change by Previous
Change Order(s) |
|
$0.00 |
|
|
Net Change by This Change
Order |
|
$46,640.00 |
|
|
New Contract Amount |
|
$286,140.00 |
|
|
|
Original Contract Time or
Completion Date |
|
June 18, 2007 |
|
|
Net Change by Previous
Change Order(s) |
|
N/A |
|
|
Net Change by This Change
Order |
|
N/A |
|
|
New Contract Time or
Completion Date |
|
N/A |
|
|
|
|
|
|
Approved By: |
|
|
|
|
|
|
|
Date: |
|
|
|
Contractor |
|
|
|
|
|
|
Date: |
|
|
|
Asst Dir of Public Works |
|
|
|
|
|
|
|
|
|
|
|