Exhibit D
8th & Pennsylvania Redevelopment Project
Phase 1: 720 E. 9th Street Site Plan Improvements
Item   Quantity Unit Unit Price Amount
1.00 General        
1.01   Mobilization 1 L.S. $20,000.00 $20,000.00
1.02   Clearing & Grubbing 1 L.S. $5,000.00 $5,000.00
1.03   Removal of Existing Structures (as necessary) 1 L.S. $5,000.00 $5,000.00
1.04   Removal of Existing Pavement (as necessary) 2008 S.Y. $7.50 $15,060.00
1.05   Construction Staking 1 L.S. $5,000.00 $5,000.00
1.06   Traffic Control 1 L.S. $2,500.00 $2,500.00
2.00 Parking Lot Improvements        
2.01   Unclassified Excavation 1 L.S. $10,000.00 $10,000.00
2.02   Compaction of Earthwork (Type B, MR-90) 1 L.S. $10,000.00 $10,000.00
2.03   Aggregate Base (36" Assumed) 1953 C.Y. $60.00 $117,180.00
2.04   Full depth Combined Curb & Gutter (Type I & Type II) 1295 L.F. $16.50 $21,366.18
2.05   Reinforced Concrete Pavement 79.8 S.Y. $65.00 $5,187.00
2.06   Pervious Asphalt Pavement (3") 1953 S.Y. $10.00 $19,530.00
2.07   Adjust Utility Cover(s) to Grade 5 Ea. $300.00 $1,500.00
2.08   Parking Lot Lighting  9 Ea. $3,500.00 $31,500.00
2.09   Interim Storm Sewer Management 1 L.S. $10,000.00 $10,000.00
2.10   Signing 1 L.S. $3,500.00 $3,500.00
Phase 5 Subtotal         $282,323.18
15% Contingency         $42,348.48
Phase 5 Total           $324,671.66
             
Phase 2:   Delaware Street Improvements
Item   Quantity Unit Unit Price Amount
1.00 General          
1.01   Mobilization 1 L.S. $75,000.00 $75,000.00
1.02   Clearing & Grubbing 1 L.S. $5,000.00 $5,000.00
1.03   Removal of Existing Structures (as necessary) 1 L.S. $5,000.00 $5,000.00
1.04   Removal of Existing Pavement (as necessary) 608 S.Y. $7.50 $4,557.83
1.05   Construction Staking 1 L.S. $20,000.00 $20,000.00
1.06   Traffic Control 1 L.S. $10,000.00 $10,000.00
2.00 Street Improvements          
2.01   Unclassified Excavation 1,043 C.Y. $7.50 $7,825.58
2.02   Compaction of Earthwork (Type B, MR-90) 608 C.Y. $5.00 $3,038.55
2.03   Fly Ash Treated Subgrade 3,453 S.Y. $7.50 $25,897.50
2.04   Aggregate Base (36" Assumed) 888 C.Y. $60.00 $53,280.00
2.05   Full depth Combined Curb & Gutter (Type I & Type II) 2,300 L.F. $16.50 $37,944.72
2.06   Asphaltic Concrete Pavement 1,815 S.Y. $35.00 $63,525.00
2.07   Reinforced Concrete Pavement 327.3 S.Y. $65.00 $21,274.50
2.08   Pervious Asphalt Pavement (3") 888 S.Y. $10.00 $8,880.00
2.09   Asphaltic Concrete Pavement (Remove & Replace) 554 S.Y. $75.00 $41,550.00
2.10   5'x4" Concrete Sidewalk 7,339 S.F. $4.50 $33,023.79
2.11   6" Sidewalk Ramps 64 S.Y. $150.00 $9,600.00
2.12   Water Hydrant Assembly Disconnect 2 Ea. $500.00 $1,000.00
2.13   Water Hydrant Assembly 2 Ea. $2,500.00 $5,000.00
2.14   Adjust Utility Cover(s) to Grade 3 Ea. $300.00 $900.00
2.15   Street Lighting  28 Ea. $3,500.00 $98,000.00
2.16   Street Trees 33 Ea. $400.00 $13,200.00
2.17   Pedestrian Canopies 3 Ea. $10,000.00 $30,000.00
2.18   Signing 1 L.S. $3,500.00 $3,500.00
3.00 Stormwater Improvements          
3.01   Improvements to Alleviate Ponding at 9th & Delaware Intersection 1 L.S. $14,375.00 $14,375.00
3.02   Stormwater Conveyance along Delaware Street 1 L.S. $88,655.00 $88,655.00
3.03   Stormwater Conveyance along 8th Street 1 L.S. $77,515.00 $77,515.00
3.04   Stormwater Conveyance across Delaware Street (as necessary) 1 L.S. $4,960.00 $4,960.00
3.05   Stormwater Conveyance across 8th Street (as necessary) 1 L.S. $9,100.00 $9,100.00
3.06   Standard Curb Inlet(s) 4 Ea. $5,000.00 $20,000.00
3.07   Extra Depth Curb Inlet(s) 3.1 V.F. $225.00 $697.50
3.08   Standard Junction Box(es) 1 Ea. $4,500.00 $4,500.00
3.09   Extra Depth Junction Box(es) 4.2 V.F. $225.00 $945.00
3.10   Standard Manhole(s) 1 Ea. $4,000.00 $4,000.00
3.11   Extra Depth Manhole(s) 3.5 V.F. $225.00 $787.50
3.12   Connect To Existing Stormwater Structure 1 Ea. $1,000.00 $1,000.00
Phase 5 Subtotal         $803,532.46
15% Contingency         $120,529.87
Phase 5 Total           $924,062.33
             
Phase 3: Poehler Site Plan Improvements
Item   Quantity Unit Unit Price Amount
1.00 General        
1.01   Mobilization 1 L.S. $35,000.00 $35,000.00
1.02   Clearing & Grubbing 1 L.S. $5,000.00 $5,000.00
1.03   Removal of Existing Structures (as necessary) 1 L.S. $5,000.00 $5,000.00
1.04   Removal of Existing Pavement (as necessary) 3125 S.Y. $7.50 $23,437.50
1.05   Construction Staking 1 L.S. $75,000.00 $75,000.00
1.06   Traffic Control 1 L.S. $7,500.00 $7,500.00
2.00 Parking Lot, Alley, & 8th Street Improvements       $0.00
2.01   Unclassified Excavation 1 L.S. $20,000.00 $20,000.00
2.02   Compaction of Earthwork (Type B, MR-90) 1 L.S. $20,000.00 $20,000.00
2.03   Aggregate Base (36" Assumed) 5025 C.Y. $60.00 $301,511.67
2.04   Full depth Combined Curb & Gutter (Type I & Type II) 160 L.F. $16.50 $2,641.32
2.05   Reinforced Concrete Pavement 905.8 S.Y. $65.00 $58,877.00
2.06   Pervious Asphalt Pavement (3") 5025 S.Y. $10.00 $50,250.00
2.07   8" Asphaltic Concrete Pavement along 8th Street 127 S.Y. $27.50 $3,493.60
2.08   Adjust Utility Cover(s) to Grade 3 Ea. $300.00 $900.00
2.09   Parking Lot Lighting  8 Ea. $3,500.00 $28,000.00
2.10   Signing 1 L.S. $1,500.00 $1,500.00
3.00 Stormwater Improvements          
3.01   Pipes from Parking Lot to Delaware System 350 L.F. $75.00 $26,250.00
Phase 5 Subtotal         $664,361.09
15% Contingency         $99,654.16
Phase 5 Total           $764,015.25
             
Phase 4: 9th, Penn, & 8th Street Improvements
Item   Quantity Unit Unit Price Amount
1.00 General        
1.01   Mobilization 1 L.S. $30,000.00 $30,000.00
1.02   Clearing & Grubbing 1 L.S. $5,000.00 $5,000.00
1.03   Removal of Existing Structures (as necessary) 1 L.S. $10,000.00 $10,000.00
1.04   Removal of Existing Pavement (as necessary) 791 S.Y. $7.50 $5,932.50
1.05   Construction Staking 1 L.S. $15,000.00 $15,000.00
1.06   Traffic Control 1 L.S. $25,000.00 $25,000.00
2.00 Street Improvements       $0.00
2.01   Unclassified Excavation 1 L.S. $30,000.00 $30,000.00
2.02   Compaction of Earthwork (Type B, MR-90) 1 L.S. $25,000.00 $25,000.00
2.03   Aggregate Base (36" Assumed) 643 C.Y. $60.00 $38,580.00
2.04   Full depth Combined Curb & Gutter (Type I & Type II) 1547 L.F. $16.50 $25,520.06
2.05   Asphaltic Concrete Pavement 156 S.Y. $35.00 $5,460.00
2.06   Reinforced Concrete Pavement 1,813.9 S.Y. $65.00 $117,905.45
2.07   Pervious Asphalt Pavement (3") 643 S.Y. $10.00 $6,430.00
2.08   5'x4" Concrete Sidewalk 5114 S.F. $4.50 $23,013.00
2.09   6" Sidewalk Ramps 39.0 S.Y. $150.00 $5,850.00
2.10   Water Hydrant Assembly Disconnect 2 Ea. $500.00 $1,000.00
2.11   Water Hydrant Assembly 2 Ea. $2,500.00 $5,000.00
2.12   Adjust Utility Cover(s) to Grade 7 Ea. $300.00 $2,100.00
2.13   Street Lighting  10 Ea. $3,500.00 $35,000.00
2.14   Street Trees 23 Ea. $400.00 $9,200.00
2.15   Signing 1 L.S. $3,500.00 $3,500.00
3.00 Stormwater Improvements       $0.00
3.01   Stormwater Conveyance along Pennsylvania Street 568 L.F. $140.00 $79,520.00
3.02   Stormwater Conveyance across Pennsylvania Street (as necessary) 68.0 L.F. $85.00 $5,780.00
3.03   Standard Curb Inlet(s) 4 Ea. $4,250.00 $17,000.00
3.04   Extra Depth Curb Inlet(s) 3.1 V.F. $225.00 $697.50
Phase 5 Subtotal         $527,488.51
15% Contingency         $79,123.28
Phase 5 Total           $606,611.78
             
Phase 5: Pennsylvania Street & Alley Improvements
Item   Quantity Unit Unit Price Amount
1.00 General        
1.01   Mobilization 1 L.S. $75,000.00 $75,000.00
1.02   Clearing & Grubbing 1 L.S. $5,000.00 $5,000.00
1.03   Removal of Existing Structures (as necessary) 1 L.S. $10,000.00 $10,000.00
1.04   Removal of Existing Pavement (as necessary) 2648 S.Y. $7.50 $19,860.00
1.05   Construction Staking 1 L.S. $20,000.00 $20,000.00
1.06   Traffic Control 1 L.S. $25,000.00 $25,000.00
2.00 Street Improvements        
2.01   Unclassified Excavation 1 L.S. $30,000.00 $30,000.00
2.02   Compaction of Earthwork (Type B, MR-90) 1 L.S. $25,000.00 $25,000.00
2.03   Fly Ash Treated Subgrade 2,256 S.Y. $5.00 $11,280.00
2.04   Aggregate Base (36" Assumed) 737 S.Y. $60.00 $44,220.00
2.05   Full depth Combined Curb & Gutter (Type I & Type II) 1778 L.F. $16.50 $29,332.88
2.06   Asphaltic Concrete Pavement 2,030 S.Y. $35.00 $71,050.00
2.07   Reinforced Concrete Pavement 149 S.Y. $65.00 $9,685.00
2.08   Pervious Asphalt Pavement (3") 737 S.Y. $10.00 $7,370.00
2.09   Remove & Replace and/or Restore Existing Brick Pavement 2,029 S.Y. $120.00 $243,538.40
2.10   5'x4" Concrete Sidewalk 4775 S.F. $4.50 $21,486.08
2.11   6" Sidewalk Ramps 35 S.Y. $150.00 $5,250.00
2.12   Adjust Utility Cover(s) to Grade 6 Ea. $300.00 $1,800.00
2.13   Street Lighting  6 Ea. $3,500.00 $21,000.00
2.14   Street Trees 3 Ea. $400.00 $1,200.00
2.15   Signing 1 L.S. $3,500.00 $3,500.00
4.00 Alleyway Improvements        
4.01   Unclassified Excavation 1 L.S. $10,000.00 $10,000.00
4.02   Compaction of Earthwork (Type B, MR-90) 1 L.S. $10,000.00 $10,000.00
4.03   Aggregate Base (36" Assumed) 1069 C.Y. $60.00 $64,140.00
4.04   Pervious Asphalt Pavement (3") 1069 S.Y. $10.00 $10,690.00
Phase 5 Subtotal         $775,402.35
15% Contingency         $116,310.35
Phase 5 Total           $891,712.71
Total Public and Private Improvement Costs:       $3,511,073.72