As you are aware, on August 14, 2006, a public meeting was held to announce the conclusion of the Wakarusa Water Reclamation Facility (WWRF) site investigation process by Black & Veatch.  The results of the investigation recommended the white site (east site) for final siting of the WWRF.  On August 29, the City Commission received the siting study report from Black & Veatch and approved the study recommendations, and authorized staff to proceed with land acquisition for the project.

 

To date, the City has acquired the following tracts on the white site:

 

          Coyne           8.0 acres

          Leary            188 acres

          Flagler           231 acres

 

Total to date:           427 acres

 

The final site proposed for initial acquisition on the white site is approximately 90 acres owned by Idessa Riley (map).  The property owner has accepted a negotiated settlement of $280,000 for the fee simple purchase of this tract.

 

City staff recommend purchase of this parcel from Idessa Riley in the amount of $280,000 and to authorize the City Manager to execute a purchase contract for this acquisition. 

 

Project Funding

Funding for land acquisition for the WWRF will come from the Utilities Dept. capital improvement reserve fund.