Memorandum

City of Lawrence Utilities Department

 

TO:

David Corliss, City Manager

FROM:

Debbie Van Saun, Asst. City Manager

Dave Wagner, Interim Utilities Director

CC:

Phillip Ciesielski, Utilities Engineer

Date:

February 15, 2007

RE:

February 20, 2007 City Commission Agenda Item

 

Please include the following item on the City Commission Agenda for consideration at the February 20, 2007 meeting. The following provides a status update on the project as well as staff recommendation for proceeding with the project:

Project History

The 2003 Waste Water Master Plan identified the need for the completion of a 7.0 million gallon per day wastewater facility discharging to the Wakarusa River by the end of year 2010.  Adding this facility and the associated infrastructure to the sanitary sewer system will allow service to a population of 150,000. 

 

In 2005, the City Commission authorized the Utilities Department to solicit proposals for engineering services for the Wakarusa Water Reclamation Facility (WWRF). The City entered into a contract with Black & Veatch for siting the treatment plant and subsequently for the conveyance corridor study, a Basis of Design Report, a Design Memorandum, and a Value Engineering Study. The City Commission subsequently approved the selection of the site and purchase of the properties.

 

Project Status:

Major efforts underway include:

 

Project Execution

Staff has reviewed the alternatives for completing the design and construction of the Wakarusa WWRF. Key objectives include having a single point of responsibility, obtaining a competitive price, ensuring a high degree of collaboration with staff, continuation of local involvement in the project, and getting a coordinated project that is completed on time and within budget. To accomplish these objectives, staff recommends that the project be completed via design/build and the project delivered by one entity responsible for the collection system and the treatment facilities. To that end, the design/build team should be selected by the Qualification Basis Selection (QBS) process.

 

This project delivery method offers the following benefits:

 

 

Project Schedule:

Updated project schedule:

 

Action Request:

Utility Department staff requests approval from the City Commission to authorize the City Manager to: