Memorandum
City of
Lawrence Utilities Department
TO:
|
David
Corliss, City Manager
|
FROM:
|
Debbie
Van Saun, Asst. City Manager
Dave
Wagner,
Interim Utilities Director
|
CC:
|
Phillip
Ciesielski, Utilities Engineer
|
Date:
|
February
15, 2007
|
RE:
|
February
20, 2007 City Commission Agenda Item
|
Please include the following item on
the City Commission Agenda for consideration at the February 20, 2007 meeting. The following provides a status
update on the project as well as staff recommendation for proceeding with the
project:
Project
History
The 2003 Waste
Water Master Plan identified the need for the completion of a 7.0
million gallon per day wastewater facility discharging to the Wakarusa River by the end of year 2010. Adding this facility and the associated infrastructure
to the sanitary sewer system will allow service to a population of 150,000.
In 2005,
the City Commission authorized the Utilities Department to solicit proposals
for engineering services for the Wakarusa Water Reclamation Facility (WWRF).
The City entered into a contract with Black & Veatch for siting the
treatment plant and subsequently for the conveyance corridor study, a Basis of
Design Report, a Design Memorandum, and a Value Engineering Study. The City Commission
subsequently approved the selection of the site and purchase of the properties.
Project
Status:
Major
efforts underway include:
- Preliminary
design work by Black and Veatch and staff continues that will deliver a
Basis of Design Report, Design Memo, Corridor Study, and Process Diagrams
and is nearing final draft stages.
- Facility
site acquisition is nearing completion and we expect to have all property
purchased this month.
- In
December 2006, staff applied to KDHE for a NPDES discharge permit and it
is expected to be issued in draft form for a 30-day comment period as
early as March. After the 30-day comment, period KDHE will consider
comments and is likely to issue a final permit shortly thereafter.
- Public
outreach, input, and dissemination of information about the project will continue
using public meetings and involvement with the project by the three
members of the Public Advisory Committee (PAC).
Project
Execution
Staff has
reviewed the alternatives for completing the design and construction of the
Wakarusa WWRF. Key objectives include having a single point of responsibility,
obtaining a competitive price, ensuring a high degree of collaboration with
staff, continuation of local involvement in the project, and getting a
coordinated project that is completed on time and within budget. To accomplish
these objectives, staff recommends that the project be completed via
design/build and the project delivered by one entity responsible for the
collection system and the treatment facilities. To that end, the design/build
team should be selected by the Qualification Basis Selection (QBS) process.
This
project delivery method offers the following benefits:
- Local
Contractors Additional Opportunities – Design-Build allows for multiple
local contractors to participate as subcontractors and this will be
required to an appropriate extent in both the RFQ and the Design-Build
contract
- Single-point
of responsibility – By awarding the project to one entity, there will be
one point of contact for all project issues, such as cost, quality, schedule,
performance, etc.
- Schedule
– Design/build allows for parallel activities to occur through the design,
procurement, construction, start-up and commissioning of the project.
These parallel activities will allow the project to be complete up to one
year ahead of the more traditional design bid build delivery. This
compressed schedule will benefit the City through cost savings associated with
project execution and management.
- Collaboration
– QBS design/build projects offer the highest degree of interaction
between staff, contractor, and engineer who jointly establish performance
expectations, costs, schedule, and quality requirements.
- Rate
Impact Control – By working with the design/build team to establish the
project schedule, City Staff can evaluate the project’s cash flow to
ensure the existing rate structure generates sufficient revenue to fund
the project.
- Value
Based Decisions – Immediate feedback on desired scope enhancements or
reductions can be made by the team based upon actual budget and/or schedule
implications.
- Continuous
Cost Control – Designs can be completed around specific equipment with the
contractor’s input regarding their desired construction staging and
methods of erection. If the project costs increase beyond the allocated
budget, immediate feedback with staffs' input can be utilized to re-direct
design efforts.
- Inflation
Control – QBS selection of a design/build team is the most efficient way
to engage a team to design and construct the desired facilities. This
allows the team to buy-out major equipment purchases, materials, and
execute subcontracts for a fixed price, reducing inflationary risks.
- Labor
Pool Commitment – The construction industry is extremely busy at this time.
By selecting a design/build team, commitment of key staff and resources
can be made in advance of other planned projects.
Project
Schedule:
Updated project
schedule:
- Complete
Basis of Design Report – March 2007
- Commence
Corridor Acquisition – May 2007 through end of year
- Complete
Design Memorandum – June 2007
- Complete
Value Engineering Study – June 2007
- Obtain
Commission Approval for Design/Build RFQ – March 6, 2007
Action
Request:
Utility
Department staff requests approval from the City Commission to authorize the
City Manager to:
- Formally
request the involvement of the PAC subgroup to assist in reviewing design
concepts for the Wakarusa WRF facilities
- Utilize design/build to design and construct the
Wakarusa WRF
- Proceed
with the selection of the design/build team utilizing a qualification
based selection process