Completed Tasks through November 28, 2006 |
Tasks for December 2006 |
Presented Siting Study to Haskell Indian Nations University. Presentation discussed Siting Study, current, and future work.
Completed review of hydraulic model for Wakarusa River. Prepared storm water mitigation plan for the initial 7 mgd facility build-out. |
Finalize Siting Study based on Comments received from City Commission, City Staff, and KDHE. Re-Submit Siting Study to Owner as required.
Continue to support City in acquisition of property.
|
Actions/Issues Important to maintain project timeline.
|
|
Decisions Needed Continue to evaluate project acceleration plan. |