Completed Tasks through November 28, 2006

Tasks for December 2006

 

Presented Siting Study to Haskell Indian Nations University.  Presentation discussed Siting Study, current, and future work.  

 

Completed review of hydraulic model for Wakarusa River.  Prepared storm water mitigation plan for the initial 7 mgd facility build-out.

 

Finalize Siting Study based on Comments received from City Commission, City Staff, and KDHE.  Re-Submit Siting Study to Owner as required.

 

Continue to support City in acquisition of property.

 

 

Actions/Issues

Important to maintain project timeline.

 

 

 

Decisions Needed

Continue to evaluate project acceleration plan.